STS-90 -- NEUROLAB
NOTE: Polishing of Columbia's windows concluded yesterday and work on payload bay flood light No. 3 is complete. Airlock ducting reconfiguration is also complete. Tunnel adapter flow rate leak testing is in work today and preparations are under way for main engine installation beginning tomorrow. Columbia's payload premate test begins today and Neurolab will be installed in the payload canister Feb. 4. The canister is currently scheduled to arrive at OPF 3 early Feb. 9 from the Operations and Checkout Building.
STS-90 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-91 -- 9TH MIR DOCKING & SPACEHAB-SMNOTE: Installation of the power drive unit for the orbiter's right external tank umbilical door continues. Work on Discovery's airlock, body flap and super lightweight tank instrumentation modification continue. Preparations are in work for auxiliary power unit installation slated for this week.
The new super lightweight external tank, to be used on STS-91, arrived at Port Canaveral yesterday and remains docked while severe weather passes through central Florida. With high winds prohibiting tugboat operations today, managers expect the tank to arrive at KSC's turn basin no earlier than tomorrow, weather permitting.
STS-91 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-88 (01-2A) ISS FIRST FLIGHTNOTE: Draining of cryogenic reactants from the power reactant storage and distribution system and aft compartment structural leak checks are complete. Technicians continue to gain access to orbiter systems and postflight inspections are under way. Flight crew equipment destow is in work. Strong back installation continues in support of payload bay door opening and SPACEHAB removal later this week.
STS-89 booster disassembly continues with segment demate preparations in work. The booster nozzles have been removed and are en route to Utah.
For automatic e-mail subscriptions to this daily Shuttle status report or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/