STS-90 -- NEUROLAB
NOTE: Leak checks of Columbia's crew module and tunnel adapter are complete. The transfer tunnel's forward extension has been installed and ammonia system servicing is complete. The payload premate test is also complete.
Aft compartment closeouts and main engine heat shield rework continues. The Neurolab payload is scheduled to arrive at the OPF on Wednesday for installation into the orbiter's cargo bay and Shuttle main engines will be installed on Friday.
STS-90 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-91 -- 9TH MIR DOCKING & SPACEHAB-SM
NOTE: Discovery's three auxiliary power units have been installed. Replacement and cycling of the power drive unit for the right-hand external tank umbilical door continues. Body flap corrosion repair and super lightweight tank instrumentation modifications continue and engine heat shield attach point mold impressions are being taken today. The orbiter's external airlock is in the OPF and will be installed into the orbiter Feb. 13. The Mir docking mechanism is being mated to the airlock today.
The new super lightweight external tank arrived in the Vehicle Assembly Building Friday afternoon to begin processing for launch on STS-91. Preparations are in work today to lift the tank and move it from the transfer aisle to the check out cell in high bay 2.
STS-91 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-88 (01-2A) ISS FIRST FLIGHT
NOTE: Endeavour's Ku band antenna assembly checks are complete. Payload disconnects are complete and SPACEHAB removal occurs today. Shuttle main engine post flight inspections are in work and removal of Endeavour's tunnel adapter is scheduled for Thursday.
STS-88 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
For automatic e-mail subscriptions to this daily Shuttle status report or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/