STS-90 -- NEUROLAB
NOTE: Columbia's main engine heat shield attach point work continues. Preparations continue for a pressure test of the orbiter's flash evaporator system on Friday. Aft compartment closeouts are ongoing, and main engine installation is now slated for next Thursday.
Replacement of the tubing insulation in Columbia's midbody is complete, and closeouts of midbody bay 7 are in work. Transfer of the Neurolab payload from the Operations and Checkout Building to the OPF begins at about 4 a.m. tomorrow. Neurolab will arrive in the payload canister at about 6 a.m. and will be installed into the orbiter after 10 a.m., weather permitting.
STS-90 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-91 -- 9TH MIR DOCKING & SPACEHAB-SM
NOTE: Body flap corrosion repair and super lightweight tank instrumentation modifications continue, and engine heat shield attach point assessments are in work. The Mir docking mechanism is being connected to Discovery's external airlock, and the airlock will be installed into the orbiter on Friday.
The super lightweight external tank has been transferred to the checkout cell in Vehicle Assembly Building high bay 2. Mission STS-91 booster stacking operations have begun on the mobile launch platform in VAB high bay 1.
STS-91 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-88 (01-2A) ISS FIRST FLIGHT
NOTE: Main propulsion system and Shuttle main engine post-flight inspections continue. Draining of the orbiter maneuvering system cross-feed lines continues, with oxidizer line draining complete and fuel line draining in work today. Tunnel adapter removal is now scheduled for Monday.
STS-88 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
For automatic e-mail subscriptions to this daily Shuttle status report or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/