STS-90 -- NEUROLAB
NOTE: Columbia’s main engine heat shield attach point work continues with match drilling in work today. Preparations for Friday’s pressure test of the orbiter’s flash evaporator system will wrap up today. Aft compartment close-outs are ongoing, and main engine installation is now slated for next Thursday.
The Neurolab payload arrived at OPF bay 3 shortly after 6 a.m. today and is now being installed into Columbia’s cargo bay.
STS-90 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-91 -- 9TH MIR DOCKING & SPACEHAB-SM
NOTE: Body flap corrosion repair and super lightweight tank instrumentation modifications continue, and engine heat shield attach point assessments are in work. While mating the Mir docking mechanism to Discovery’s external airlock, KSC technicians noticed some galling on several of the bolts that connect the two components. NASA engineers are evaluating the possibility of replacing the bolts and resuming airlock processing early next week.
STS-91 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-88 (01-2A) ISS FIRST FLIGHT
NOTE: Draining of hypergolic fuel from Endeavour’s orbiter maneuvering system (OMS) cross-feed lines is complete. Preparations for next week’s OMS pod functional testing are under way. Main propulsion system and Shuttle main engine post-flight inspections continue. Tunnel adapter removal is now scheduled for Monday.
STS-88 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
For automatic e-mail subscriptions to this daily Shuttle status report or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/