STS-90 -- NEUROLAB
NOTE: Columbia’s main engine heat shield attach point work continues. The orbiter’s flash evaporator system will undergo pressure tests today. Aft compartment close-outs are ongoing, and main engine installation is slated for next Thursday. With external tank and solid rocket booster close-outs nearing completion, ET/SRB mate is slated for Feb. 19.
The Neurolab payload was installed into Columbia’s cargo bay yesterday and payload interface verification testing is scheduled for next week.
STS-90 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-91 -- 9TH MIR DOCKING & SPACEHAB-SM
NOTE: Installation of Discovery’s forward reaction control system is complete. Body flap corrosion repair and super lightweight tank instrumentation modifications continue, and engine heat shield attach point assessments are in work. NASA engineers continue to evaluate the galling noticed on about 13 out of 96 bolts that connect the Mir docking mechanism to Discovery’s external airlock. Managers may opt to change-out the flawed bolts and resume airlock processing next week.
STS-91 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-88 (01-2A) ISS FIRST FLIGHT
NOTE: Preparations for next week’s OMS pod functional testing continue. Main propulsion system and Shuttle main engine post-flight inspections continue. Tunnel adapter removal is now scheduled for Monday and fuel cell voltage testing begins Wednesday.
STS-88 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
For automatic e-mail subscriptions to this daily Shuttle status report or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/