STS-90 -- NEUROLAB
NOTE: Work on the orbiter's main engine heat shield attach points continues. Main engine installation will begin once this work is complete. Neurolab's transfer tunnel installation has been rescheduled for Monday.
STS-90 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-91 -- 9TH MIR DOCKING & SPACEHAB-SM
NOTE: The auxiliary power unit leak and functional checks continue. The airlock will be installed into the orbiter's payload bay no earlier than late next week. Installation of Discovery's right-hand orbiter maneuvering system also begins next week.
STS-91 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-88 (01-2A) ISS FIRST FLIGHT
NOTE: Tunnel adapter removal is complete. Orbital maneuvering system pod functional tests and fuel cell voltage tests will continue today. A functional test of the forward reaction control system is set for Tuesday.
STS-88 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
For automatic e-mail subscriptions to this daily Shuttle status report or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/