STS-89 -- 8th MIR DOCKING & SPACEHAB DM
NOTE: The hot-fire of all three auxiliary power units (APU) was successfully completed last night with satisfactory results. The crew of mission STS-89 continues to take part in the Terminal Countdown Demonstration Test being held at KSC this week. Tomorrow, they will go through simulated launch day activities including entering the orbiter Endeavour for a simulated main engine ignition and cut-off. They will depart for their homes in Houston tomorrow afternoon to complete their pre-mission training. Currently, the crew is scheduled to return to KSC on Jan. 19 for final launch activities.
STS-89 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-90 -- NEUROLABNOTE: Installation of Columbia's fuel cells is complete and functional tests are in work. Also in work are operations to remove the remote manipulator system robotic arm, functional tests of the orbiter maneuvering system, and auxiliary power unit leak and functional checks.
STS-90 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-91 -- 9th MIR DOCKING & SPACEHAB-SMNOTE: Leak checks of the orbiter's freon loop are complete. Preparations are in work to remove and replace fuel cell No. 2 and to prepare the forward reaction control system to be sent to the Hypergol Maintenance Facility for routine inspections.
For automatic e-mail subscriptions to this daily Shuttle status report or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/