KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      THURSDAY, JANUARY 15, 1998 (4:00 PM EST)

      KSC Public Affairs Contact: Joel Wells (fax 407-867-2692)
      E-mail: Joel.Wells-1@ksc.nasa.gov

      Launch Viewing Information


      MISSION: STS-89 -- 8th MIR DOCKING & SPACEHAB DM

      STS-89 images

      • VEHICLE: Endeavour/OV-105
      • LOCATION: Launch Pad 39A
      • TARGET KSC LAUNCH DATE/TIME: Jan. 22, 1998 with a preferred time of 9:48 p.m. EST
      • LAUNCH WINDOW: 10 minute window (opens at 9:43 p.m. EST)
      • MIR DOCKING DATE/TIME: Jan. 24 at about 3:12 p.m.
      • MIR UNDOCKING DATE/TIME: Jan. 29 at about 11:52 a.m.
      • TARGET KSC LANDING DATE/TIME: Jan. 31, 1998 at 5:36 p.m.
      • MISSION DURATION: 8 days, 19 hours, 48 minutes
      • CREW: Wilcutt, Edwards, Dunbar, Anderson, Reilly, Sharipov, Thomas (up), Wolf (down)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees

      NOTE: Testing on microwave scanning beam landing system No. 3 is complete, following a recent decoder replacement. Endeavour's aft compartment close-outs are in work through the weekend and ordnance connections began early this morning. Payload bay doors are slated for closure on Friday. Hypergolic system pressurization is in work and will continue through Saturday.

      Shuttle engineers continue to evaluate a small leak on a hydraulic line for auxiliary power unit No. 3. A Russian motion control computer and air conditioning unit are slated to be installed into the SPACEHAB module on Sunday, for use on the Mir space station. To prepare for installation activities, workers Friday will conduct an exercise with a full scale mock-up of the air conditioning unit to confirm installation procedures and clearances.

      STS-89 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • SPACEHAB stow (Jan. 16 and 18)
      • Payload bay doors closed for flight (Jan. 16)
      • Launch countdown begins (Jan. 19 at 7 p.m.)
      • Flight crew arrival (Jan. 19 at 3:30 p.m.)

      MISSION: STS-90 -- NEUROLAB

      STS-90 images
      • VEHICLE: Columbia/OV-102
      • LOCATION: OPF bay 3
      • TARGET KSC LAUNCH DATE/TIME: April 2, 1998 at 1:19 p.m.
      • LAUNCH WINDOW: 2 hours, 30 minutes
      • TARGET KSC LANDING DATE/TIME: April 18, l998 at 12:09 p.m.
      • MISSION DURATION: 15 days, 21 hours, 50 minutes
      • CREW: Searfoss, Atlman, Linnehan, Williams, Hire, Buckey, Pawelczyk
      • ORBITAL ALTITUDE and INCLINATION: 150 nautical miles/39 degrees

      NOTE: Voltage tests on Columbia's fuel cells are complete and APU leak and functional checks concluded yesterday. Power reactant storage and distribution system checks are in work and are expected to conclude today. Replacement of payload bay floodlights No. 1 and No. 5 and aft flight deck reconfiguration continue. Orbiter maneuvering system functional tests are proceeding on schedule.

      STS-90 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Tunnel adapter installation (Jan. 21)
      • Payload premate test (Jan. 28)
      • Payload installed into orbiter (Jan. 30)
      • Shuttle main engine installation (Jan. 30)

      MISSION: STS-91 -- 9th MIR DOCKING & SPACEHAB-SM
      • VEHICLE: Discovery/OV-103
      • LOCATION: OPF bay 2
      • TARGET KSC LAUNCH DATE/TIME: May 28 at 8:33 p.m.
      • LAUNCH WINDOW: 7-10 minutes
      • TARGET KSC LANDING DATE/TIME: June 7 at about 12:17 a.m.
      • MISSION DURATION: 9 days, 3 hours, 44 minutes
      • CREW: Precourt, Gorie, Lawrence, Chang-Diaz, Kavandi, Thomas (down)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees

      NOTE: Technicians have completed efforts to remove residual oxidizer and fuel from the orbiter maneuvering system (OMS) cross-feed lines and will remove the right hand OMS pod tomorrow. The pod will then undergo a valve change-out in the Hypergol Maintenance Facility. Replacement of Discovery's fuel cell No. 2 is complete as fuel cell monitoring modifications continue. Work to install instrumentation that supports the new Super Lightweight External Tank continues and body flap corrosion repairs proceed on schedule.

      Work to install instrumentation that supports the new Super Lightweight External Tank continues and body flap corrosion repairs proceed on schedule.

      STS-91 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Removal of right-hand OMS pod (Jan. 16)
      • Fuel cell voltage test (Jan. 20)
      • Remote manipulator system installed (Jan. 23)

      --end--

      For automatic e-mail subscriptions to this daily Shuttle status report or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/