KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      THURSDAY, JANUARY 29, 1998 (2:19 PM EST)

      KSC Public Affairs Contact: Joel Wells (fax 407-867-2692)
      E-mail: Joel.Wells-1@ksc.nasa.gov

      Launch Viewing Information


      MISSION: STS-89 -- 8TH MIR DOCKING & SPACEHAB DM
      Flight Day 8

      STS-89 images

      • VEHICLE: Endeavour/OV-105
      • LOCATION: On orbit
      • KSC OFFICIAL LAUNCH DATE/TIME: Jan. 22, 1998 at 9:48:15 p.m. EST
      • OFFICIAL MIR DOCKING DATE/TIME: Jan. 24 at 3:14 p.m.
      • OFFICIAL MIR UNDOCKING DATE/TIME: Jan. 29 at 11:56 a.m.
      • KSC LANDING DATE/TIME: Jan. 31, 1998 at 5:35 p.m.
      • MISSION DURATION: 8 days, 19 hours, 17 minutes
      • CREW: Wilcutt, Edwards, Dunbar, Anderson, Reilly, Sharipov, Thomas (up), Wolf (down)
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees

      NOTE: Endeavour’s systems continued to perform very well as all transfer activities were completed and undocking preparations began this morning. The orbiter undocked from Mir on time at 11:56 a.m. today. At Hangar AF, solid rocket booster disassembly is in work and aft skirt removal is planned for today.

      Forecasters expect generally favorable weather conditions for Saturday’s planned Shuttle landing at KSC. Early predictions indicate scattered clouds at 2,000 feet and broken at 25,000 feet; visibility at 7 miles; winds from the northeast at 5-6 mph; temperature 67 degrees and relative humidity 54 percent. Touchdown of Shuttle Endeavour is targeted to occur on the first of two landing opportunities at about 5:35 p.m.


      MISSION: STS-90 -- NEUROLAB

      STS-90 images
      • VEHICLE: Columbia/OV-102
      • LOCATION: OPF bay 3
      • TARGET KSC LAUNCH DATE/TIME: April 2, 1998 at 1:19 p.m.
      • LAUNCH WINDOW: 2 hours, 30 minutes
      • TARGET KSC LANDING DATE/TIME: April 19, l998 at 12:07 p.m.
      • MISSION DURATION: 16 days, 21 hours, 48 minutes
      • CREW: Searfoss, Atlman, Linnehan, Williams, Hire, Buckey, Pawelczyk
      • ORBITAL ALTITUDE and INCLINATION: 150 nautical miles/39 degrees

      NOTE: Technicians began work to replace 3 thrusters last night on Columbia’s orbiter maneuvering system and will continue efforts through midnight tonight. Leak checks of the OMS begin tomorrow. Gaseous nitrogen servicing of the water spray boiler is complete. Replacement of the No. 3 payload bay floodlight and installation of a Spacelab fluid line are complete.

      STS-90 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Payload premate test begins (Feb. 3)
      • Shuttle main engine installation complete (Feb. 4)
      • Payload installed into orbiter (Feb. 9)
      • Shuttle main engine heat shield installation begins (Feb. 11)
      • Payload interface verification test (Feb. 12)

      MISSION: STS-91 -- 9TH MIR DOCKING & SPACEHAB-SM
      • VEHICLE: Discovery/OV-103
      • LOCATION: OPF bay 2
      • TARGET KSC LAUNCH DATE/TIME: May 28 at 8:05 p.m.
      • LAUNCH WINDOW: 7-10 minutes
      • TARGET KSC LANDING DATE/TIME: June 7 at about 3:36 p.m.
      • MISSION DURATION: 9 days, 19 hours, 31 minutes
      • CREW: Precourt, Gorie, Lawrence, Chang-Diaz, Kavandi, Thomas (down), Ryumin
      • ORBITAL ALTITUDE and INCLINATION: 160 nautical miles/51.6 degrees

      NOTE: Pressure checks of Discovery’s flash evaporator system (FES), loop No. 1 and fuel cell functional checks are complete. Tests of FES loop No. 2 are in work today. Preparations for tomorrow’s fuel cell voltage tests are in progress. Work on the orbiter’s airlock, body flap and super lightweight tank instrumentation modification continue.

      STS-91 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Fuel cell voltage test (Jan. 30)
      • External airlock installation (Feb. 4)

      --end--

      For automatic e-mail subscriptions to this daily Shuttle status report or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/


      Go to the Previous Space Shuttle Status Report
      Go to the Next Space Shuttle Status Report

      Go to the Status Reports Home Page