KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      MONDAY, JUNE 22, 1998 (2:00 PM EDT)

      KSC Public Affairs Contact: Joel Wells (fax: 407-867-2692)

      Launch Viewing Information


      MISSION: STS-95 -- SPACEHAB-SM, SPARTAN & HOST

      STS-95 images

      • VEHICLE: Discovery/OV-103
      • LOCATION: Orbiter Processing Facility bay 2
      • TARGET KSC LAUNCH DATE/TIME: Oct. 29 at 2 p.m. EDT
      • TARGET KSC LANDING DATE/TIME: Nov. 7 at 12:04 p.m. EDT
      • MISSION DURATION: 8 days, 22 hours and 4 minutes
      • CREW: Brown, Lindsey, Parazynski, Robinson, Duque, Makai, Glenn
      • ORBITAL ALTITUDE and INCLINATION: 310 nautical miles/28.45 degrees

      NOTE: Validation of Discovery's electrical power systems and payload removal efforts are complete. Preparations to drain the orbiter maneuvering system (OMS) reactant storage tanks are in work and OMS thruster replacement efforts are scheduled to begin this week. Leak checks of the flash evaporator system and post flight inspections of the Shuttle main engines are ongoing.

      STS-95 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Hypergolic propellant off load complete (June 23)
      • Orbiter docking system base removal (July 6)
      • OMS thruster replacement complete (July 10)

      MISSION: STS-88 -- FIRST FLIGHT INTERNATIONAL SPACE STATION
      UNITY (Node-1)

      STS-88 images

      • VEHICLE: Endeavour/OV-105
      • LOCATION: OPF bay 1
      • TARGET KSC LAUNCH DATE/TIME: Dec. 3 time TBD
      • TARGET KSC LANDING DATE/TIME: Dec. 14 time TBD
      • MISSION DURATION: 11 days
      • CREW: Cabana, Sturckow, Currie, Ross, Newman
      • ORBITAL ALTITUDE and INCLINATION: 173 nautical miles/51.6 degrees

      NOTE: Endeavour's water spray boiler checks are complete. Connection of the right hand OMS pod oxidizer transfer lines is complete and the fuel transfer lines will be connected later this week. Main engine heat shield attach point rework begins this week and today workers will conduct checks of the fuel cell No. 3 water relief panel.

      STS-88 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Payload premate test (July 6)

      MISSION: STS-93 -- Advanced X-ray Astrophysics Facility (AXAF)

      STS-93 images

      • VEHICLE: Columbia/OV-102
      • LOCATION: OPF bay 3
      • TARGET KSC LAUNCH DATE/TIME: Jan. 21, 1999 time TBD
      • TARGET KSC LANDING DATE/TIME: Jan. 26, 1999 time TBD
      • LAUNCH WINDOW: 43 minutes
      • MISSION DURATION: 4 days, 23 hours, 7 minutes
      • CREW: Collins, Ashby, Hawley, Coleman, Tognini
      • ORBITAL ALTITUDE and INCLINATION: 153 nautical miles/28.45 degrees

      NOTE: Drag chute installation is in progress. Deservicing of Columbia's environmental control and life support system is under way and water spray boiler replacement work begins this week. Window polishing is in work. Columbia's auxiliary power units No. 3 and No. 1 will be installed into the orbiter beginning Wednesday.

      --end--

      For automatic e-mail subscriptions to these Shuttle status reports or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/


      Go to the Previous Space Shuttle Status Report
      Go to the Next Space Shuttle Status Report

      Go to the Status Reports Home Page