STS-90 -- NEUROLAB
NOTE: Leak checks on Columbia's crew module and Ku-band testing are complete. Main engine heat shields are being installed and aft compartment close-outs are in work. Payload bay door inspections are under way and the doors are scheduled to be closed for flight this afternoon. Spacelab internal close-outs are in progress as well.
STS-90 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-91 -- 9TH AND FINAL MIR DOCKING, SPACEHAB-SM
NOTE: Discovery's right-hand orbiter maneuvering system pod was installed yesterday and electrical mates are complete. Preparations to install the orbiter's body flap continue and installation of auxiliary power unit No. 1 concludes today. The airlock is scheduled to be installed in the orbiter this afternoon. In the Vehicle Assembly Building, stacking operations for the STS-91 solid rocket boosters continue and will conclude next week.
STS-91 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-88 -- FIRST FLIGHT INTERNATIONAL SPACE STATIONNOTE: Preparations for next week's removal of Endeavour's main engines continue and heat shield removal is in work today. Technicians are troubleshooting a helium isolation valve on the orbiter's reaction control system and work is also under way to replace a line that supplies gaseous nitrogen to the Spacelab.
STS-88 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
NOTE on ATLANTIS (OV-104): Atlantis remains at Palmdale, CA, undergoing scheduled maintenance and orbiter modifications. The vehicle is due to be ferried back to KSC in August.
For automatic e-mail subscriptions to this daily Shuttle status report or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/