![]() FRIDAY, MAY 29, 1998 (11:38 AM EDT) STS-91 -- 9TH AND FINAL MIR DOCKING, SPACEHAB-SM, Alpha Magnetic Spectrometer (AMS)
NOTE: The STS-91 launch countdown begins tomorrow at 9 p.m. and all prelaunch preparations continue on schedule. The contingency space suits are installed in the orbiter's airlock. Aft main engine compartment close-outs continue with installation of the aft doors slated for tomorrow morning. Preliminary weather forecasts indicate a 40 percent chance that weather could prohibit launch activities on Tuesday. The primary concern is for seabreeze thunderstorms with associated showers and anvil clouds. The forecast calls for scattered clouds at 4,000 feet and broken clouds at 30,000 feet; visibility of 7 miles (in thunderstorms possibly 2 miles); winds from the southeast at 12 knots peaking to 18 knots; a temperature of 83 degrees F and relative humidity of 63 percent. STS-91 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-88 -- FIRST FLIGHT INTERNATIONAL SPACE STATIONUNITY (Node-1)
NOTE: Installation of Endeavour's forward reaction control system is complete and interface checks are planned for today. Auxiliary power unit leak and functional testing continues and main engine heat shield attach point work is under way. Technicians will install hydraulic pump No. 3 today. Endeavour's payload bay doors will be opened today and later the Ku-band antenna will be deployed. In the Vehicle Assembly Building, solid rocket booster joint close-outs continue. STS-93 -- Advanced X-ray Astrophysics Facility (AXAF)
NOTE: Columbia's orbiter maneuvering system leak and functional testing is complete. Ammonia off load from water spray boiler No. 3 concluded yesterday and electrical checks are in work today. Technicians are preparing to remove Columbia's extended duration orbiter (EDO) pallet today. Main propulsion system leak and functional testing begins today. STS-93 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
For automatic e-mail subscriptions to this daily Shuttle status report or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription. To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release." Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/ |