KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      TUESDAY, NOVEMBER 10, 1998 (10:20 AM EST)

      Launch Viewing Information

      MISSION: STS-88 -- 1ST FLIGHT INTERNATIONAL SPACE STATION
      UNITY CONNECTING MODULE

      STS-88 images

      • VEHICLE: Endeavour/OV-105
      • LOCATION: Launch Pad 39A
      • TARGET KSC LAUNCH DATE/TIME: Dec. 3 at about 3:59 a.m. EST
      • TARGET KSC LANDING DATE/TIME: Dec. 14 at about 11:13 p.m. EST
      • LAUNCH WINDOW: 5 - 10 minutes
      • MISSION DURATION: 11 days, 18 hours
      • CREW: Cabana, Sturckow, Currie, Ross, Newman, Krikalev
      • ORBITAL ALTITUDE and INCLINATION: 173 nautical miles/51.6 degrees

      NOTE: At Launch Pad 39A, orbiter and secondary payload interface verification test (IVT) preparations are complete. Workers have also completed the IVT for Endeavour's primary payload, the Unity connecting module. Unity is slated for payload bay installation Nov. 13. This week, forward reaction control system connections are scheduled and preparations for next week's hypergolic propellant loading activities continue on schedule.

      STS-88 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Unity installed inside orbiter payload bay (Nov. 13)
      • Payload sharp edge inspection (Nov. 16)
      • Prelaunch propellant loading (Nov. 17)
      • Orbiter aft compartment closeouts begin (Nov. 19)
      • Ordnance installation (Nov. 23)
      • Flight crew equipment stow (Nov. 24)

      MISSION: STS-93 -- Advanced X-ray Astrophysics Facility (AXAF)

      STS-93 images

      • VEHICLE: Columbia/OV-102
      • LOCATION: OPF bay 3
      • TARGET KSC LAUNCH DATE/TIME: no earlier than March 18, time TBD
      • TARGET KSC LANDING DATE/TIME: no earlier than March 23, time TBD
      • LAUNCH WINDOW: 47 minutes
      • MISSION DURATION: 5 days
      • CREW: Collins, Ashby, Hawley, Coleman, Tognini
      • ORBITAL ALTITUDE and INCLINATION: 153 nautical miles/28.45 degrees

      NOTE: Columbia's main engine securing is complete. Filling of the water spray boiler's core is also complete. Orbiter aft compartment closeouts and main engine/main propulsion system integrated tests are in progress. Engine heat shield installation is in work. Structural modal test preparations continue and auxiliary power unit lubrication servicing occurs later this week. Next week, integrated hydraulic and flight control system testing begins. Solid rocket booster stacking operations continue in the Vehicle Assembly Building.


      MISSION: STS-96 -- 2nd U.S. INTERNATIONAL SPACE STATION FLIGHT
      SPACEHAB DOUBLE MODULE

      STS-96 images

      • VEHICLE: Discovery/OV-103
      • LOCATION: OPF bay 1
      • TARGET KSC LAUNCH DATE/TIME: May 13, 1999 at 12:33 p.m. EST
      • TARGET KSC LANDING DATE/TIME: May 24, 1999 at 8:47 a.m. EST
      • MISSION DURATION: 11 days (+1)
      • CREW: Rominger, Husband, Ochoa, Jernigan, Barry, Payette, Malenchenko
      • ORBITAL ALTITUDE and INCLINATION: 173 nautical miles/51.6 degrees

      NOTE: Technicians have completed removal of the drag chute mortar from Discovery's aft compartment. Primary access has been gained to the orbiter's crew module, and power reactant storage and distribution system tank purging is complete. Main engine purge efforts concluded yesterday. Orbiter access platforms are being installed today in the aft compartment and preparations for tomorrow's payload bay door opening are in progress. Payload removal will conclude early next week.


      MISSION: STS-101 -- 3rd INTERNATIONAL SPACE STATION FLIGHT
      SPACEHAB-DM/ICC
      • VEHICLE: Atlantis/OV-104
      • LOCATION: OPF bay 2
      • TARGET KSC LAUNCH DATE/TIME: August 5, 1999
      • TARGET KSC LANDING DATE/TIME: August 15, 1999
      • LAUNCH WINDOW: 10 minutes
      • MISSION DURATION: 10 days
      • ORBITAL ALTITUDE and INCLINATION: 173 nautical miles/51.6 degrees

      NOTE: Replacement of Atlantis' window No. 4 is complete. Remote manipulator system installation continues and will conclude early next week. Leak checks on the orbiter's oxygen system crossover valves are in work. The auxiliary power unit lines will be connected next Wednesday.

      --end--

      For automatic e-mail subscriptions to these Shuttle status reports or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/


      Author: Joel Wells / NASA Public Affairs
      Curator: Kay Grinter (kay.grinter-1@ksc.nasa.gov) / Information Dynamics, Inc.

      Go to the Previous Space Shuttle Status Report
      Go to the Next Space Shuttle Status Report

      Go to the Status Reports Home Page