![]() FRIDAY, OCTOBER 16, 1998 (2:45 PM EDT) STS-95 -- SPACEHAB-SM, SPARTAN & HOST
NOTE: Pressure decay tests on Discovery's crew cabin and SPACEHAB module are complete. Mass memory unit (MMU) No. 2 was installed in the orbiter yesterday and MMU loading occurs today. SPACEHAB early stow activities are in work today and preparations are under way for next week's orbiter aft compartment closeouts. STS-95 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-88 -- 1ST FLIGHT INTERNATIONAL SPACE STATIONUNITY CONNECTING MODULE
NOTE: Endeavour is hard mated to the external tank in Vehicle Assembly Building high bay 3. Tail service mast mates are in work today. KSC launch controllers are conducting the standard launch countdown simulation today in firing room No. 3. Umbilical mates and leak checks are slated for tonight. The Shuttle Interface Test begins at about 3 a.m. on Monday. The Shuttle is scheduled to roll out to Launch Pad 39A on Wednesday beginning at 7 a.m. STS-88 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-93 -- Advanced X-ray Astrophysics Facility (AXAF)
NOTE: The AXAF payload is now expected to arrive at KSC in early January and the payload premate test will move accordingly to mid-November. Shuttle managers are reviewing the impact to the STS-93 major milestones. STS-101 -- 3rd FLIGHT INTERNATIONAL SPACE STATIONSPACEHAB-DM/ICC
NOTE: Preparations are in work for removal of Atlantis' simulated orbiter maneuvering system pods on Monday. Technicians continue to gain access to the orbiter's midbody compartment and receiving inspections proceed on schedule. Orbiter electrical system validations continue and troubleshooting of the aft compartment power control assembly are in work. For automatic e-mail subscriptions to these Shuttle status reports or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription. To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release." Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/ Author: Joel Wells / NASA Public Affairs Curator: Kay Grinter (kay.grinter-1@ksc.nasa.gov) / Information Dynamics, Inc. |