KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      WEDNESDAY, OCTOBER 21, 1998 (4:59 PM EDT)

      Launch Viewing Information

      MISSION: STS-95 -- SPACEHAB-SM, SPARTAN & HOST

      STS-95 images

      • VEHICLE: Discovery/OV-103
      • LOCATION: Launch Pad 39B
      • KSC LAUNCH DATE/TIME: Oct. 29 at 2 p.m. EST
      • TARGET KSC LANDING DATE/TIME: Nov. 7 at 11:49 a.m. EST
      • LAUNCH WINDOW: 2 hours and 30 minutes
      • MISSION DURATION: 8 days, 21 hours and 49 minutes
      • CREW: Brown, Lindsey, Parazynski, Robinson, Duque, Mukai, Glenn
      • ORBITAL ALTITUDE and INCLINATION: 300 nautical miles/28.45 degrees

      NOTE: Discovery’s aft compartment closeouts and flight crew equipment stowage continue on schedule. The orbiter’s aft compartment doors will be installed at midnight tomorrow. Ordnance installation is in work through Thursday. Payload bay closeouts begin tomorrow and the payload bay doors will be closed for flight tomorrow night. Routine prelaunch inspections of the external tank and solid rocket boosters are slated for tomorrow.

      STS-95 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Payload bay doors closed for flight (Oct. 22)
      • SPACEHAB late stow (Oct. 26)
      • Launch countdown begins (Oct. 26 at 8 a.m.)

      MISSION: STS-88 -- 1ST FLIGHT INTERNATIONAL SPACE STATION
      UNITY CONNECTING MODULE

      STS-88 images

      • VEHICLE: Endeavour/OV-105
      • LOCATION: Launch Pad 39A
      • TARGET KSC LAUNCH DATE/TIME: Dec. 3 at about 3:55 a.m. EST
      • TARGET KSC LANDING DATE/TIME: Dec. 14 at about 10:19 p.m. EST
      • LAUNCH WINDOW: 5 - 10 minutes
      • MISSION DURATION: 11 days, 18 hours
      • CREW: Cabana, Sturckow, Currie, Ross, Newman, Krikalev
      • ORBITAL ALTITUDE and INCLINATION: 173 nautical miles/51.6 degrees

      NOTE: Shuttle Endeavour is now hard down on Launch Pad 39A. The Shuttle began its 3.4-mile trip from the Vehicle Assembly Building to the pad at about 2:18 a.m. today. Launch pad validations are under way and tonight workers will conduct a planned hot fire of Endeavour’s auxiliary power units No. 1 and No. 3. The Rotating Service Structure will be extended around the vehicle early Thursday morning and main engine flight readiness testing follows later in the day. The Unity Connecting Module payload arrives at the pad Monday for installation in the pad’s payload changeout room.

      STS-88 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Auxiliary power unit hot fire test (Oct. 21)
      • Launch pad validations (Oct. 21 - 22)
      • Unity payload arrives at Pad 39A (Oct. 26)

      --end--

      For automatic e-mail subscriptions to these Shuttle status reports or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/


      Author: Joel Wells / NASA Public Affairs
      Curator: Kay Grinter (kay.grinter-1@ksc.nasa.gov) / Information Dynamics, Inc.

      Go to the Previous Space Shuttle Status Report
      Go to the Next Space Shuttle Status Report

      Go to the Status Reports Home Page