KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      TUESDAY, SEPTEMBER 29, 1998 (10:41 AM EDT)

      KSC Public Affairs Contact: Joel Wells (fax: 407-867-2692)

      Launch Viewing Information

      MISSION: STS-95 -- SPACEHAB-SM, SPARTAN & HOST

      STS-95 images

      • VEHICLE: Discovery/OV-103
      • LOCATION: Launch Pad 39B
      • TARGET KSC LAUNCH DATE/TIME: Oct. 29 at 2 p.m. EST
      • TARGET KSC LANDING DATE/TIME: Nov. 7 at 12:04 p.m. EST
      • LAUNCH WINDOW: 2 hours and 30 minutes
      • MISSION DURATION: 8 days, 22 hours and 4 minutes
      • CREW: Brown, Lindsey, Parazynski, Robinson, Duque, Mukai, Glenn
      • ORBITAL ALTITUDE and INCLINATION: 300 nautical miles/28.45 degrees

      NOTE: Launch pad validations are complete at pad 39B and the Rotating Service Structure has been extended around Shuttle Discovery. Installation of the vertical payloads into the pad's payload changeout room is complete and the orbiter's payload bay doors will be opened this morning. The SPACEHAB, Spartan and HOST payloads will be installed into the orbiter tomorrow and payload interface verification testing begins Thursday.

      STS-95 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Vertical payloads installed into orbiter (Sept. 30)
      • Prelaunch hypergolic propellants loaded into onboard storage tanks (Oct. 5 - 7)
      • Flight crew arrival at KSC (Oct. 6 at about 3 p.m.)
      • Terminal Countdown Demonstration Test (Oct. 8-9)

      MISSION: STS-88 -- FIRST FLIGHT INTERNATIONAL SPACE STATION
      UNITY CONNECTING MODULE

      STS-88 images

      • VEHICLE: Endeavour/OV-105
      • LOCATION: OPF bay 1
      • TARGET KSC LAUNCH DATE/TIME: Dec. 3 at 4:45 a.m. EST
      • TARGET KSC LANDING DATE/TIME: Dec. 14 at 11:14 p.m. EST
      • LAUNCH WINDOW: 5 - 10 minutes
      • MISSION DURATION: 11 days, 18 hours and 29 minutes
      • CREW: Cabana, Sturckow, Currie, Ross, Newman, Krikalev
      • ORBITAL ALTITUDE and INCLINATION: 173 nautical miles/51.6 degrees

      NOTE: Endeavour's payload bay doors remain open while the orbiter undergoes work in the midbody compartment. Cabin air circulation system inspection and maintenance is complete. Inspections of the orbiter's various onboard cameras continue. Potable water servicing and radiator functional tests are ongoing.

      STS-88 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Crew Equipment Interface Test (Oct. 3)
      • Payload bay door closure (Oct. 7)
      • Orbiter weight and center of gravity testing (Oct. 10)
      • Orbiter transfer to Vehicle Assembly Building (Oct. 12)

      MISSION: STS-93 -- Advanced X-ray Astrophysics Facility (AXAF)

      STS-93 images

      • VEHICLE: Columbia/OV-102
      • LOCATION: OPF bay 3
      • TARGET KSC LAUNCH DATE/TIME: Jan. 21, 1999 at 11:26 a.m. EST
      • TARGET KSC LANDING DATE/TIME: Jan. 26, 1999 at 10:33 a.m. EST
      • LAUNCH WINDOW: 47 minutes
      • MISSION DURATION: 4 days, 23 hours, 7 minutes
      • CREW: Collins, Ashby, Hawley, Coleman, Tognini
      • ORBITAL ALTITUDE and INCLINATION: 153 nautical miles/28.45 degrees

      NOTE: Columbia's payload bay doors are open and cycling tests of the Ku-band electronics assembly are complete. Auxiliary power unit testing is in work today.


      MISSION: STS-101 -- 3rd FLIGHT INTERNATIONAL SPACE STATION
      SPACEHAB-DM/ICC
      • VEHICLE: Atlantis/OV-104
      • LOCATION: OPF bay 2
      • TARGET KSC LAUNCH DATE/TIME: August 5, 1999
      • TARGET KSC LANDING DATE/TIME: August 15, 1999
      • LAUNCH WINDOW: 10 minutes
      • MISSION DURATION: 10 days
      • ORBITAL ALTITUDE and INCLINATION: 173 nautical miles/51.6 degrees

      NOTE: Orbiter Atlantis was towed from the Shuttle Landing Facility to OPF bay 2 yesterday. With work platforms in place around the vehicle, technicians will begin deconfiguring Atlantis from its current ferry flight setup. Next week, the aerodynamic and protective tail cone will be removed from the Shuttle orbiter's aft engine compartment. Workers will powerup the vehicle Monday and the payload bay doors will be opened. Removal of the simulated orbiter maneuvering system pods begins late next week.

      --end--

      For automatic e-mail subscriptions to these Shuttle status reports or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/