STS-99 -- SHUTTLE RADAR TOPOGRAPHY MISSION (SRTM)NOTE: Yesterday, workers removed the Shuttle Radar Topography Mission payload from Endeavour's payload bay and today technicians are establishing access to the orbiter's midbody for planned wiring inspections. Inspections are expected to begin this weekend. With wiring inspection and maintenance plans now in place, implementation efforts are in progress across the Shuttle fleet.
Shuttle managers are reviewing several manifest options this week and could establish the new target launch dates for 1999 as early as next week. Engineers must first define the time that will be needed to complete the fleet-wide wiring maintenance effort. Shuttle Endeavour currently remains slated for launch in early October.
STS-103 -- 3rd HUBBLE SPACE TELESCOPE SERVICING MISSION (HST-3)NOTE: Wiring inspections are about 25 percent complete aboard Shuttle Discovery. Earlier access allowed workers to begin inspections on Discovery this week. Technicians have completed installation of Discovery's external airlock hatch. Electrical connections are complete for the orbiter's forward reaction control system. Main engine heatshield installation is in work.
STS-101 -- 3rd INTERNATIONAL SPACE STATION FLIGHT - SPACEHAB DOUBLE MODULE/ICCNOTE: Orbiter Atlantis is currently being stored inside Vehicle Assembly Building high bay 2, awaiting the departure of Shuttle Endeavour from OPF bay 2. Wiring inspections in Atlantis' payload bay are complete and wireless video modifications have resumed. Atlantis will be moved to the VAB transfer aisle next week to accommodate external tank transfer activities.
NOTE: Orbiter Columbia is undergoing routine post-flight deservicing in Orbiter Processing Facility bay 3. Also, workers are preparing the spacecraft for its upcoming Orbiter Maintenance Down Period (OMDP) in Palmdale, CA. Columbia is scheduled to be mounted atop NASA's modified Boeing 747 on Sept. 22. The ferry flight is scheduled to begin on Sept. 23 with an overnight stop at Luke Air Force Base in Arizona. Current plans have Columbia arriving in Palmdale, CA on Sept. 24. Because the orbiter can not be flown through precipitation of any kind, ferry flight plans are contingent upon weather conditions in the flight path.
For automatic e-mail subscriptions to these Shuttle status reports or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/