KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      THURSDAY, JUNE 10, 1999 (2:09 PM EDT)

      MISSION: STS-93 -- Chandra X-ray Observatory

      STS-93 images

      • VEHICLE: Columbia/OV-102
      • LOCATION: Launch Pad 39B
      • TARGET KSC LAUNCH DATE/TIME: No earlier than July 20, 1999 at 12:36 a.m. EDT (under review)
      • TARGET KSC LANDING DATE/TIME: July 24, 1999 at 11:31 p.m. EDT
      • LAUNCH WINDOW: 46 minutes
      • MISSION DURATION: 4 days, 23 hours
      • CREW: Collins, Ashby, Hawley, Coleman, Tognini
      • ORBITAL ALTITUDE and INCLINATION: 153 nautical miles/28.45 degrees

      NOTE: Launch pad validations are complete at Pad 39B. Columbia's auxiliary power units (APU) No. 1 and No. 3 have completed hotfire testing and APU No. 2 will follow next week. Main engine flight readiness testing concluded yesterday. Planned cycling of the orbiter's payload bay doors also concluded yesterday. Preparations are in work for the Helium Signature Test scheduled through tomorrow. Columbia's hypergolic loading begins Monday.

      The Chandra/IUS combination will be placed into the transportation canister on June 18. The payload will be moved to the launch pad on June 19 and installed inside Columbia's cargo bay on June 24.

      STS-93 SCHEDULED OPERATIONAL MILESTONES (dates are target only):

      • Shuttle Main Engine testing complete (June 6)
      • Chandra payload transferred to Pad 39B (June 19)
      • Payload installed inside cargo bay (June 24)

      MISSION: STS-99 -- SHUTTLE RADAR TOPOGRAPHY MISSION (SRTM)

      • VEHICLE: Endeavour/OV-105
      • LOCATION: OPF bay 2
      • TARGET KSC LAUNCH DATE/TIME: Sept. 16, 1999 at 8:47 a.m. EDT
      • TARGET KSC LANDING DATE/TIME: Sept. 27, 1999 at 12:52 p.m. EDT
      • LAUNCH WINDOW: 2 hours and 30 minutes
      • MISSION DURATION: 11 days, 4 hours and 5 minutes
      • CREW: Kregel, Gorie, Kavandi, Voss, Mohri, Thiele
      • ORBITAL ALTITUDE and INCLINATION: 126 nautical miles/57 degrees

      NOTE: Installation of Endeavour's main engine No. 1 is complete and installation of engines No. 2 and No. 3 continue this week. Modifications to the main engine dome heat shields continue. Wireless video installation efforts continue on schedule. Modifications to the final section of line on freon coolant loop No. 2 are in work.


      MISSION: STS-103 -- 3rd HUBBLE SPACE TELESCOPE SERVICING MISSION (HST-3)

      • VEHICLE: Discovery/OV-103
      • LOCATION: OPF bay 1
      • TARGET KSC LAUNCH DATE/TIME: Oct. 14, 1999 at 5:42 a.m. EDT
      • TARGET KSC LANDING DATE/TIME: Oct. 23, 1999 at 3:09 a.m. EDT
      • LAUNCH WINDOW: 42 minutes
      • MISSION DURATION: 8 days, 21 hours and 27 minutes
      • CREW: Brown, Kelly, Smith, Foale, Grunsfeld, Nicollier, Clervoy
      • ORBITAL ALTITUDE and INCLINATION: 317 nautical miles/28.45 degrees

      NOTE: Workers have completed orbiter access installation and the payload bay doors were opened yesterday. Preparations are in work for Monday's scheduled payload removal. Preparations are also under way for Discovery's hypergolic deservicing set to begin next week. Routine post-flight inspections of the orbiter continue.


      MISSION: STS-101 -- 3rd INTERNATIONAL SPACE STATION FLIGHT - SPACEHAB DOUBLE MODULE/ICC

      • VEHICLE: Atlantis/OV-104
      • LOCATION: OPF bay 3
      • TARGET KSC LAUNCH DATE/TIME: December 2, 1999
      • TARGET KSC LANDING DATE/TIME: December 13, 1999
      • LAUNCH WINDOW: 5-10 minutes
      • MISSION DURATION: 10 days and 19 hours
      • CREW: Halsell, Horowitz, Weber, Lu, Williams, Malenchenko, Morukov
      • ORBITAL ALTITUDE and INCLINATION: 173 nautical miles/51.6 degrees

      NOTE: Leak and functional testing of Atlantis' ammonia system is complete. Wireless video modifications continue. Mass spectrometer leak checks on the orbiter's fuel cell power plant continue. UHF system checks are under way.

      --end--

      For automatic e-mail subscriptions to these Shuttle status reports or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.

      To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."

      Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm

      Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/


      Author: Joel Wells / NASA Public Affairs
      Curator: Kay Grinter (kay.grinter-1@ksc.nasa.gov) / Information Dynamics, Inc.

      Go to the Previous Space Shuttle Status Report
      Go to the Next Space Shuttle Status Report

      Go to the Status Reports Home Page