STS-93 -- Chandra X-ray Observatory
NOTE: Repair work on the payload ground handling mechanism at Launch Pad 39B was successfully completed over the weekend and that system is ready to support payload operations at the pad. However, workers encountered problems with the Rotating Service Structure (RSS) last night and were unable to move it away from the vehicle. The Chandra/IUS payload was not transferred to the launch pad today as planned and remains in the transportation canister at KSC's Vertical Processing Facility.
Following successful RSS troubleshooting today and tomorrow morning, the payload will be delivered to the pad Thursday morning. With an early Thursday morning payload arrival at the pad, managers plan to install the Chandra/IUS payload into Columbia's payload bay no earlier than Sunday. A hot fire test of auxiliary power unit No. 2 has also been postponed to either Wednesday or Thursday. Terminal Countdown Demonstration Test activities continue, but Thursday's dress rehearsal may start two hours late to accommodate additional work and pad clearance requirements. Columbia's launch remains targeted for no earlier than July 20.
STS-93 SCHEDULED OPERATIONAL MILESTONES (dates are target only):
STS-99 -- SHUTTLE RADAR TOPOGRAPHY MISSION (SRTM)NOTE: Modifications to the final section of line on freon coolant loop No. 2 are complete and routine leak checks are in work. Installation of Endeavour's window No. 1 is also complete. Workers are preparing to install the orbiter's external airlock this week. Payload premate test efforts are also scheduled this week.
STS-103 -- 3rd HUBBLE SPACE TELESCOPE SERVICING MISSION (HST-3)NOTE: Removal of Discovery's main engines began last night with engines No. 2 and No. 3. Forward reaction control system checks concluded yesterday and orbital maneuvering system pod functional tests are ongoing. Removal of the transfer tunnel adapter is scheduled this week.
STS-101 -- 3rd INTERNATIONAL SPACE STATION FLIGHT - SPACEHAB DOUBLE MODULE/ICCNOTE: Installation of Atlantis' left-hand orbital maneuvering system is complete and checks are in work. TACAN antenna installation, wireless video modifications, and mass spectrometer leak checks on the orbiter's fuel cell power plant continue.
For automatic e-mail subscriptions to these Shuttle status reports or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.
To remove your name from the list at any time, send an e-mail address to domo@news.ksc.nasa.gov. In the body of the message (not the subject line), type (no quotes) "unsubscribe shuttle-status", or "unsubscribe ksc-press-release."
Status reports and other NASA publications are available on the World Wide Web at: http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm
Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://shuttle.nasa.gov/