Work in progress: Orbiter Discovery has been mated to the external tank and solid rocket boosters stack in VAB high bay 1. Electrical and mechanical connections will conclude late Friday and the orbiter/external tank umbilical mate occurs Saturday. Over the weekend, workers will begin preparations for the engine No. 3 replacement work scheduled to happen at the launch pad. Managers currently plan to transfer Discovery out to Launch Pad 39B Tuesday, Nov. 9 beginning at about 2 a.m.
Payload managers plan to transfer the Hubble Servicing Mission cargo to the launch pad Monday, Nov. 8 with installation into the orbiter slated for Nov. 12.
KSC managers are developing the remainder of Discovery's prelaunch processing schedule and expect to brief Shuttle program managers at a meeting Monday morning. Program managers are likely to set a new target launch date for STS-103 after the meeting.
For automatic e-mail subscriptions to these Shuttle status reports or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.