KENNEDY SPACE CENTER SPACE SHUTTLE STATUS REPORT
      TUESDAY, NOVEMBER 9, 1999 (11:30 AM EST)

      MISSION: STS-103 -- 3rd HUBBLE SPACE TELESCOPE SERVICING MISSION (HST-3)

      • VEHICLE: Discovery/OV-103
      • LOCATION: VAB
      • TARGET KSC LAUNCH DATE/TIME: December 6 at 2:37 a.m. EST
      • TARGET KSC LANDING DATE/TIME: December 16 at 12:45 a.m. EST
      • LAUNCH WINDOW: 42 minutes
      • MISSION DURATION: 10 days
      • CREW: Brown, Kelly, Smith, Foale, Grunsfeld, Nicollier, Clervoy
      • ORBITAL ALTITUDE and INCLINATION: 317 nautical miles/28.45 degrees

      Work in progress: Space Shuttle Discovery is scheduled to roll out to Launch Pad 39B on Saturday, Nov. 13, with first motion slated for 2 a.m. The remainder of Discovery's processing schedule leads to a target launch date of Dec. 6.

      Workers have already removed the damaged range safety cable and replacement efforts begin later today. Engineers plan to retest the range safety system Wednesday and close-out the work area Thursday. The damaged range safety cable relays a redundant emergency destruction signal between the solid rocket boosters (SRB) in the unlikely event of a contingency. The cable being replaced runs from the right-hand SRB forward attach point, through the external tank and connects to the left-hand booster. The cable was damaged during close-out operations causing yesterday's test failure.

      Since the orbiter will remain in the VAB for cable replacement, Shuttle managers have decided to replace Discovery's main engine No. 3 in the VAB as well. Engine replacement efforts are in work and will conclude Thursday. Engine close-outs and verifications will be performed at the pad.

      The Hubble Servicing Mission cargo has been transferred into the payload change-out room at Launch Pad 39B and installation into the orbiter's payload bay is slated for Nov. 16.

      Major Processing Milestones:
      Shuttle to the Launch Pad . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (Nov. 13)
      Payload installed into orbiter . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (Nov. 16)
      Terminal Countdown Demonstration Test (crew dress rehearsal) . . . . (Nov. 17)
      Shuttle main engine test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . (Nov. 23)

      --end--

      For automatic e-mail subscriptions to these Shuttle status reports or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.


      Author: Joel Wells / NASA Public Affairs
      Curator: Kay Grinter (Kay.Grinter@jbosc.ksc.nasa.gov) / InDyne, Inc.

      Previous Report | Status Reports | News | Media Resources | Next Report