MISSION: STS-99 --
Shuttle Radar Topography Mission (SRTM) |
|
|
| VEHICLE |
Endeavour/OV-105 |
| LOCATION |
Pad 39A |
| TARGET KSC LAUNCH
DATE/TIME |
No
earlier than Jan. 31, 2000 at 12:47 p.m. EST |
| TARGET KSC LANDING
DATE/TIME |
Feb.
11, 2000 at 4:52 p.m. EST |
| LAUNCH
WINDOW |
2 hours and 2 minutes |
| MISSION
DURATION |
11 days and 4 hours |
| CREW |
Kregel, Gorie, Kavandi, Voss, Mohri, Thiele
|
| ORBITAL ALTITUDE and
INCLINATION |
126 nautical miles/57 degrees |
|
|
| Work in
progress |
At Launch Pad 39A, preparations for Endeavour's
upcoming launch continue on schedule. Orbiter aft compartment close-outs are
going well and the aft doors are slated for installation on Wednesday. Shuttle
ordnance installation begins today and flight crew equipment stowage continues
through next week.
Engineering evaluation of Endeavour's thermal tiles continues. The analysis will
determine if any additional tile work is required on Endeavour prior to launch,
and if so, what schedule impacts may exist. To date, only two tiles have been
removed from the orbiter's nose and will be replaced in parallel with standard
work.
Engineers are also considering a strengthening modification for four camera
mounts located in the orbiter's payload bay. If the modifications are needed,
the payload bay doors must be opened to allow work on the forward and aft
bulkhead cameras early next week, with no impact to the current schedule.
|
| Processing
Milestones |
|
Ordnance
installation complete |
Jan. 24 |
|
|
Orbiter
aft comparment close-outs |
Jan. 26 |
|
|
Flight
crew equipment stowage complete |
Jan. 26 |
|
|
Flight
crew arrives at KSC |
Jan. 27
at noon |
|
|
Launch
Countdown begins |
Jan. 28
at 5:30 p.m. |
|
|
|
|
|
MISSION:
STS-101 -- 3rd ISS Flight (2A.2) - SPACEHAB DM |
|
|
| VEHICLE |
Atlantis/OV-104 |
| LOCATION |
Orbiter Processing Facility bay 3 |
| TARGET KSC LAUNCH
DATE/TIME |
No earlier than
April 13, 2000 at about 9:30 p.m. |
| TARGET KSC LANDING
DATE/TIME |
April 24, 2000 |
| LAUNCH
WINDOW |
about
10 minutes |
| MISSION
DURATION |
10 days and 19 hours |
| CREW |
Halsell, Horowitz, Weber, Lu, Williams, Malenchenko and Morukov |
| ORBITAL ALTITUDE and
INCLINATION |
173 nautical miles/51.6 degrees |
|
|
| Work in
progress |
Orbiter maneuvering system functional tests were
completed earlier this week. Servicing of Atlantis' freon coolant loop No. 2
concluded Wednesday. Wiring inspections and repairs continue in the orbiter's
aft and midbody compartments. Checks on the Ku-band antenna and TACAN system are
also under way.
|
|
|
|
MISSION:
STS-92
-- 4th ISS Flight (3A) - Z-1 Truss, PMA-3 |
|
|
| VEHICLE |
Discovery/OV-103 |
| LOCATION |
OPF bay 1 |
| TARGET KSC LAUNCH
DATE/TIME |
No earlier
than June 14, 2000 at 8:42 p.m. EDT |
| TARGET KSC LANDING
DATE/TIME |
June 24, 2000 at 5:10 p.m. EDT |
| LAUNCH
WINDOW |
10 minutes |
| MISSION
DURATION |
10 days |
| CREW |
Duffy,
Melroy, Wakata, Chiao, Wisoff, Lopez-Alegria and
McArthur |
| ORBITAL ALTITUDE
and INCLINATION |
173 nautical miles/51.6
degrees |
|
|
| Work in
progress |
Functional tests on Discovery's orbiter maneuvering
system are under way. Orbiter main landing gear inspections are in work this
week and thermal protection system waterproofing efforts are ongoing.
|
|
|
|
|