This is an orbiter processing report and does not reflect the chronological order of upcoming Space Shuttle Flights. Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm on the KSC Home Page for the latest schedule of future Shuttle missions.

MISSION: STS-101 -- 3rd ISS Flight (2A.2a) - SPACEHAB DM

VEHICLE Atlantis/OV-104
LOCATION On orbit
TARGET KSC LAUNCH DATE/TIME May 19, 2000 at about 6:11 a.m. EDT
TARGET KSC LANDING DATE/TIME May 29, 2000 at about 2:19 a.m.
LAUNCH WINDOW 5 minutes
MISSION DURATION 9 days, 20 hours, 7 minutes
CREW Halsell, Horowitz, Weber, Williams, Voss, Helms, Usachev
ORBITAL ALTITUDE and INCLINATION 173 nautical miles/51.6 degrees
Shuttle Processing Note
At Hangar AF, the solid rocket booster disassembly process continues on schedule. Forward and aft skirts were removed from both boosters yesterday and nozzle removal occurs today. All segment hardware and solid rocket motor inspections indicate booster performance was normal and no abnormal damage was sustained. Standard groundwork is underway at the Shuttle Landing Facility this week in preparation for Monday's planned landing of Shuttle Atlantis.


MISSION: STS-92 -- 5th ISS Flight (3A) -- Z-1 Truss, PMA-3

VEHICLE Discovery/OV-103
LOCATION OPF bay 1
TARGET KSC LAUNCH DATE/TIME Sept. 21, 2000 at 3:55 a.m. EDT
TARGET KSC LANDING DATE/TIME Oct. 2, 2000 at 5:11 p.m.
MISSION DURATION 10 days
CREW Duffy, Melroy, Wakata, Chiao, Wisoff, Lopez-Alegria, McArthur
ORBITAL ALTITUDE and INCLINATION 173 nautical miles/51.6 degrees
Shuttle Processing Note
Leak checks of Discovery's main propulsion system are complete. Engine heat shield installation is in progress. This week drag chute door and frame evaluation if scheduled. Payload bay door closure occurred Monday.

In the Vehicle Assembly Building, workers are lubricating the 250-ton crane before continuing booster stacking operations. Managers currently plan to resume stacking of the right-hand solid rocket booster early next week. Once the right hand booster is completed, engineers will begin a planned assessment of booster field joints for about 2 weeks. Left-hand booster stacking will commence following that effort.


MISSION: STS-97 -- 6th ISS Flight (4A) -- PV Module P6

VEHICLE Endeavour/OV-105
LOCATION OPF bay 2
TARGET KSC LAUNCH DATE/TIME Nov. 29, 2000 at 10:50 p.m. EDT
TARGET KSC LANDING DATE/TIME Dec. 9, 2000 at 1:40 a.m.
MISSION DURATION 9 days
CREW Jett, Bloomfield, Tanner, Noriega, Garneau
ORBITAL ALTITUDE and INCLINATION 173 nautical miles/51.6 degrees
Shuttle Processing Note
Testing of Endeavour's power reactant storage and distribution system is complete. Preparation is in work to replace the right-hand orbiter maneuvering system engine. Technicians are installing the orbiter's main landing gear wheels and tires. Later this week, workers will install the docking system on the orbiter's airlock.


 

For automatic e-mail subscriptions to these Shuttle status reports or KSC-originated press releases, send an Internet electronic mail message to domo@news.ksc.nasa.gov. In the body of the message (not the subject line) type the words "subscribe shuttle-status", or "subscribe ksc-press-release" (do not use quotation marks). The system will reply with a confirmation via e-mail of each subscription.


KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines

Page Last Revised

Page & Curator Information

09/21/2000

Curator: Kay Grinter (Kay.Grinter-1@ksc.nasa.gov) -- InDyne, Inc./
Web Development: JBOSC Web Development Team
A Service of the NASA/KSC External Relations and Business Development Directorate
JoAnn H. Morgan, Director