MISSION: STS-100 -- 9th
ISS Flight (6A) - Raffaello MPLM, SSRMS |
| Vehicle |
Endeavour/OV-105 |
| Location |
Launch Pad 39A |
| KSC Launch Date/Time |
April 19, 2001, at 2:41 p.m. EDT |
| KSC Landing Date/Time |
April 30, 2001, at 10:00 a.m. EDT |
| Mission Duration |
10 days, 19 hours and 19 minutes |
| Crew |
Rominger, Ashby, Hadfield, Parazynski,
Phillips, Guidoni, Lonchakov |
| Orbit Altitude and Inclination |
173 nautical miles/51.6 degrees |
|
|
|
Shuttle
Processing Note (orbiter
processing notes) |
Last night, workers installed Shuttle Endeavour's aft compartment doors concluding aft closeout efforts. Standard external tank purge activities are complete and launch countdown preparations continue.
Loading of the flight crew equipment into the crew module concludes today. No significant work is planned over the weekend, and the seven-member flight crew is scheduled to arrive at KSC's Shuttle Landing Facility at about 10:30 a.m. Monday. The countdown clock begins at 6 p.m. Monday. |
|
|
|
Upcoming
Milestones (dates are targets only) |
| Flight crew equipment early
stow |
April 12-13 |
| Flight crew arrival at KSC |
April 16 at about 10:30 a.m. |
| Launch countdown starts |
April 16 at 6 p.m. |
|
|
|
|