MISSION: STS-98 -- 7th ISS Flight (5A) - U.S. Laboratory

Vehicle Atlantis/OV-104
Location Launch Pad 39A
Target KSC Launch Date/Time January 19, 2001 at 2:11 a.m. EST
Target KSC Landing Date/Time January 29, 2001 at 10:37 p.m. EST
Launch Window less than 5 minutes
Mission Duration 10 days, 20 hours
Crew Cockrell, Polansky, Curbeam, Jones, Ivins
Orbit Altitude and Inclination 177 nautical miles/51.6 degrees
 

Shuttle Processing Note  (mission processing summary)

Activities at launch pad 39A continue on schedule for launch of Shuttle Atlantis on Jan. 19. Work at the pad this weekend includes finalizing launch pad validations and the completion of the Terminal Countdown Demonstration Test. The U.S. Laboratory "Destiny" is scheduled for installation into Atlantis' payload bay this weekend.

Early next week, work will begin to load hypergolic propellants into the orbiter's storage tanks. This should be complete by Wednesday, Jan. 10 and will be followed by the main engine flight readiness test and ordnance installation activities. Following final payload testing, the payload bay doors will be closed for flight Thursday, Jan. 11.

 

Upcoming Milestones  (dates are targets only)

Terminal Countdown Demonstration Test complete January 6
Begin loading propellant into Atlantis' onboard tanks January 8
Shuttle Main Engine testing January 10
Orbiter aft compartment close-outs begin January 11
Ordnance installation begins January 13

 

Status reports and other NASA publications are available on the World Wide Web at:  http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm. Information about the countdown and mission can be accessed electronically via the Internet at:  http://www-pao.ksc.nasa.gov/kscpao/shuttle/countdown/ and at http://spaceflight.nasa.gov/

 
KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines

Page Last Revised

Page & Curator Information

01/15/01

Curator: Kay Grinter (Kay.Grinter-1@ksc.nasa.gov) -- InDyne, Inc./
Web Development: JBOSC Web Development Team
A Service of the NASA/KSC External Relations and Business Development Directorate
JoAnn H. Morgan, Director