MISSION: STS-98 -- 7th ISS Flight (5A) - U.S. Laboratory

Vehicle Atlantis/OV-104
Location Vehicle Assembly Building high bay 3
Target KSC Launch Date/Time no earlier than Feb. 6, 2001 at 6:37 p.m. EST
Target KSC Landing Date/Time Feb. 17, 2001 at 2:05 p.m. EST
Launch Window less than 5 minutes
Mission Duration 10 days, 19 hours, 28 minutes
Crew Cockrell, Polansky, Curbeam, Jones, Ivins
Orbit Altitude and Inclination 177 nautical miles/51.6 degrees
 

Shuttle Processing Note  (mission processing summary)

Work continues on schedule for the rollout of Space Shuttle Atlantis on Friday morning. KSC Shuttle system engineers in the launch control room successfully completed the Shuttle Interface Test this morning. 

In the Vehicle Assembly Building, work continues to close-out the solid rocket boosters and install the systems tunnel covers. Tomorrow, workers will remove work platforms in VAB high bay 3 and complete final preparations for the Shuttle's move to Launch Pad 39A. After Atlantis returns to the launch pad, crews will transfer the partial STS-100 booster stack from storage in VAB high bay 2 back to high bay 3 on Saturday.
 

 

Status reports and other NASA publications are available on the World Wide Web at:  http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm. Information about the countdown and mission can be accessed electronically via the Internet at:  http://www-pao.ksc.nasa.gov/kscpao/shuttle/countdown/ and at http://spaceflight.nasa.gov/

 
KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines

Page Last Revised

Page & Curator Information

01/24/2001

Curator: Kay Grinter (Kay.Grinter-1@ksc.nasa.gov) -- InDyne, Inc./