MISSION: STS-98 -- 7th ISS Flight (5A) - U.S. Laboratory

Vehicle Atlantis/OV-104
Location Launch Pad 39A
Target KSC Launch Date/Time Feb. 7, 2001 at 6:11 p.m. EST
Target KSC Landing Date/Time Feb. 18, 2001 at about 12:58 p.m. EST
Launch Window less than 5 minutes
Mission Duration 10 days, 18 hours and 47 minutes
Crew Cockrell, Polansky, Curbeam, Jones, Ivins
Orbit Altitude and Inclination 177 nautical miles/51.6 degrees
 

Shuttle Processing Note  (mission processing summary)

Following U.S. Lab installation yesterday, workers completed final inspections inside Space Shuttle Atlantis' payload bay and then closed the payload bay doors for flight. Orbiter aft compartment closeouts continue and Shuttle ordnance installation began today. Technicians plan to install the aft compartment doors Friday morning and ordnance installation concludes tomorrow. Pressurization of Atlantis' onboard hypergolic storage tanks occurs Thursday.
 

Upcoming Milestones  (dates are targets only)

Shuttle ordnance installation complete February 1
Orbiter aft compartment closeouts complete February 2
Flight crew arrives at KSC February 4 about 1:30 p.m.
Launch countdown begins February 4 at 10 p.m.

 

MISSION: STS-102 -- 8th ISS Flight (5A.1) - Leonardo MPLM

Vehicle Discovery/OV-103
Location Orbiter Processing Facility (OPF) bay 1
Target KSC Launch Date/Time March 8, 2001, at about 7:00 a.m. EST
Target KSC Landing Date/Time March 20, 2001, at about 1:00 a.m. EST
Launch Window less than 5 minutes
Mission Duration 11 days
Crew Wetherbee, Kelly, Thomas, Richards; (up) Voss, Helms, Usachev; (down) Shepherd, Gidzenko, Krikalev
Orbit Altitude and Inclination 177 nautical miles/51.6 degrees
 

Shuttle Processing Note 

Discovery's water tank checks are complete and forward compartment closeouts will conclude today. Tonight, workers will prepare the orbiter transporter for rollover operations. Weight and center of gravity tests are ongoing. Managers plan to transfer Discovery to the VAB Thursday evening.
 

MISSION: STS-100 -- 9th ISS Flight (6A) - Raffaello MPLM, SSRMS

Vehicle Endeavour/OV-105
Location Orbiter Processing Facility (OPF) bay 2
Target KSC Launch Date/Time April 19, 2001, at 2:04 p.m. EDT
Target KSC Landing Date/Time April 30, 2001, at 9:56 a.m. EDT
Mission Duration 11 days
Crew Rominger, Ashby, Hadfield, Parazynski, Phillips, Guidoni, Lonchakov
Orbit Altitude and Inclination 177 nautical miles/51.6 degrees
 

Shuttle Processing Note 

Installation of the two gaseous nitrogen tanks that support the power reactant storage and distribution system continues. Technicians are installing the drag chute and plan to service freon coolant loop No. 1 this week.
 

Status reports and other NASA publications are available on the World Wide Web at:  http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm. Information about the countdown and mission can be accessed electronically via the Internet at:  http://www-pao.ksc.nasa.gov/kscpao/shuttle/countdown/ and at http://spaceflight.nasa.gov/

 
KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines

Page Last Revised

Page & Curator Information

01/31/2001

Curator: Kay Grinter (Kay.Grinter-1@ksc.nasa.gov) -- InDyne, Inc./
Web Development: JBOSC Web Development Team
A Service of the NASA/KSC External Relations and Business Development Directorate
JoAnn H. Morgan, Director