March 15, 2001

 
2001 Year at a Glance

Status Reports

February Status Reports
 
Note

This is an orbiter processing report and does not necessarily reflect the chronological order of upcoming Space Shuttle flights.  Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm for the latest schedule of future Shuttle missions.

 

 

MISSION: STS-102 -- 8th ISS Flight (5A.1) - Leonardo MPLM

Vehicle Discovery/OV-103
Location On orbit
Official KSC Launch Date/Time March 8, 2001, at 6:42:09.059 a.m. EST
Target KSC Landing Date/Time March 20, 2001, at about 1:56 a.m. EST
Mission Duration 11 days, 19 hours and 14 minutes
Crew Wetherbee, Kelly, Thomas, Richards; (up) Voss, Helms, Usachev; (down) Shepherd, Gidzenko, Krikalev
Orbit Altitude and Inclination 122 nautical miles/51.6 degrees
 

Note 

Now in its fifth day of docked operations with the International Space Station, Space Shuttle Discovery remains in excellent health on orbit. Post-flight inspections have revealed both solid rocket boosters to be in good condition. Walk-down inspections of Launch Pad 39B confirmed no unusual damage or debris following last week's launch.
 

MISSION: STS-100 -- 9th ISS Flight (6A) - Raffaello MPLM, SSRMS

Vehicle Endeavour/OV-105
Location Orbiter Processing Facility (OPF) bay 2
Target KSC Launch Date/Time April 19, 2001, at 3:12 p.m. EDT
Target KSC Landing Date/Time April 30, 2001, at 11:10 a.m. EDT
Mission Duration 11 days
Crew Rominger, Ashby, Hadfield, Parazynski, Phillips, Guidoni, Lonchakov
Orbit Altitude and Inclination 173 nautical miles/51.6 degrees
 

Shuttle Processing Note 

Orbiter Endeavour's midbody and aft engine compartments have been closed-out in preparation for rollover to the Vehicle Assembly Building. Weight and center of gravity tests begin tomorrow and first motion is scheduled for Saturday at about 9 a.m. Technicians are troubleshooting an overhead switch panel in the crew module while rollover preparations proceed on schedule.
 

MISSION: STS-104 -- 10th ISS Flight (7A) - Airlock

Vehicle Atlantis/OV-104
Location OPF bay 3
KSC Launch Date/Time NET June 8, 6:50 p.m. EDT
KSC Landing Date/Time June 19, 2:24 p.m. EST
Mission Duration 11 days
Crew Lindsey, Hobaugh, Kavandi, Gernhardt, Reilly
Orbit Altitude and Inclination 122 nautical miles/51.6 degrees
 

Shuttle Processing Note

Orbiter Atlantis' post-ferry deconfiguration concluded last week with tail cone removal. Main engine heat shield removal is in work today and technicians begin main engine removal Friday morning. Forward reaction control system (FRCS) checks are in work today and flash evaporator system checks occur later this week.

 

COLUMBIA/OV-102 Post-Ferry Processing

In OPF bay 1, Columbia's simulated FRCS pod is being removed today. The tail cone will be removed Friday and the payload bay doors will be opened for processing activities. Columbia is scheduled to remain in OPF 1 through late April and then move to the VAB for storage until OPF bay 3 becomes available. Columbia's next flight is under review, but could occur as early as this fall.

 

Status reports and other NASA publications are available on the World Wide Web at:  http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm. Information about the countdown and mission can be accessed electronically via the Internet at:  http://www-pao.ksc.nasa.gov/kscpao/shuttle/countdown/ and at http://spaceflight.nasa.gov/

 
KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines

Page Last Revised

Page & Curator Information

03/15/2001

Curator: Kay Grinter (Kay.Grinter-1@ksc.nasa.gov) -- InDyne, Inc./
Web Development: JBOSC Web Development Team
A Service of the NASA/KSC External Relations and Business Development Directorate
JoAnn H. Morgan, Director