March 22, 2001

 
2001 Year at a Glance

Status Reports

February Status Reports
 
Note

This is an orbiter processing report and does not necessarily reflect the chronological order of upcoming Space Shuttle flights.  Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm for the latest schedule of future Shuttle missions.

 

MISSION: STS-100 -- 9th ISS Flight (6A) - Raffaello MPLM, SSRMS

Vehicle Endeavour/OV-105
Location En route to Launch Pad 39A
Target KSC Launch Date/Time April 19, 2001, at 3:12 p.m. EDT
Target KSC Landing Date/Time April 30, 2001, at 11:10 a.m. EDT
Mission Duration 11 days
Crew Rominger, Ashby, Hadfield, Parazynski, Phillips, Guidoni, Lonchakov
Orbit Altitude and Inclination 173 nautical miles/51.6 degrees
 

Shuttle Processing Note  (orbiter processing notes) 

Space Shuttle Endeavour rolled out of the Vehicle Assembly Building today at about 9:50 a.m. Solid rocket booster closeout inspections slightly delayed first motion, and Endeavour is now expected to arrive at the pad before 4 p.m. Once at the pad, routine launch pad validations commence, verifying all vehicle and facility interfaces.
 

Upcoming Milestones  (dates are targets only)

Shuttle main engine flight readiness test March 25
Shuttle helium signature leak test complete March 28
Terminal Countdown Demonstration Test March 29-30
Orbiter prelaunch propellant loading begins April 2
Flight Readiness Review April 5
 
 

MISSION: STS-104 -- 10th ISS Flight (7A) - Airlock

Vehicle Atlantis/OV-104
Location OPF bay 3
Target KSC Launch Date/Time NET June 14, 4:15 p.m. EDT
Target KSC Landing Date/Time June 25, 12:30 p.m. EDT
Mission Duration 11 days
Crew Lindsey, Hobaugh, Kavandi, Gernhardt, Reilly
Orbit Altitude and Inclination 122 nautical miles/51.6 degrees
 

Shuttle Processing Note  (orbiter processing notes)

Atlantis' orbital maneuvering system pods are undergoing standard functional tests today. Workers are preparing for orbiter fuel cell voltage tests on Saturday. Additional forward reaction control system inspections are ongoing.

 

MISSION: STS-105 -- 11th ISS Flight (7A.1) - Leonardo MPLM

Vehicle Discovery/OV-103
Location OPF bay 2
Target KSC Launch Date/Time July 12, 2001, at 4:45 a.m. EDT
Target KSC Landing Date/Time July 22, 2001, at 12:29 a.m. EDT
Mission Duration 10 days
Crew Horowitz, Struckow, Barry, Forrester; (up) Culbertson, Dezhurow, Turin; (down) Voss, Helms, Usachev; 
Orbit Altitude and Inclination 122 nautical miles/51.6 degrees

 

Shuttle Processing Note  (orbiter processing notes)

Orbiter Discovery arrived at the OPF at about 9 a.m. Wednesday. Post-flight inspection of Discovery's lower surface thermal protection system revealed a total of 42 debris hits with 10 measuring one inch or larger in dimension. Main engine drying is in work today along with power reactant storage and distribution system offloading activities. Discovery's payload bay doors will be opened Saturday and payload removal begins Tuesday.
 

MISSION: STS-109 -- HST Servicing Mission 3B

Vehicle Columbia/OV-102
Location OPF bay 1
Target KSC Launch Date/Time November 19, 2001, under review
Target KSC Landing Date/Time November 30, 2001, under review
Mission Duration TBD
Crew TBD 
Orbit Altitude and Inclination 308 nautical miles/28.5 degrees
 

Shuttle Processing Note  (orbiter processing notes

Preparation continues for the removal of Columbia's simulated orbital maneuvering system pods later this week. Columbia is scheduled to remain in OPF 1 through late April and then move to the VAB for storage until OPF bay 3 becomes available. Columbia's next flight is under review, but could occur as early as this fall.
 

Status reports and other NASA publications are available on the World Wide Web at:  http://www-pao.ksc.nasa.gov/kscpao/kscpao.htm. Information about the countdown and mission can be accessed electronically via the Internet at:  http://www-pao.ksc.nasa.gov/kscpao/shuttle/countdown/ and at http://spaceflight.nasa.gov/

 
KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines

Page Last Revised

Page & Curator Information

04/26/2001

Curator: Kay Grinter (Kay.Grinter-1@ksc.nasa.gov) -- InDyne, Inc./
Web Development: JBOSC Web Development Team
A Service of the NASA/KSC External Relations and Business Development Directorate
JoAnn H. Morgan, Director