|
MISSION:
STS-108 --
12th ISS
Flight (UF1) - Raffaello MPLM |
| Vehicle |
Endeavour/OV-105 |
| Target KSC Launch
Date/Time |
Nov. 29, 2001 at 7:35
p.m. EST |
| Target KSC Landing
Date/Time |
Dec. 10, 2001 |
| Mission Duration |
11 days |
| Crew |
Gorie, Kelly,
Godwin, Tani; (ISS-4 up) Onufrienko, Bursch, Walz; (ISS-3
down) Culbertson, Dezhurov, Tyurin |
| Orbital Insertion
Altitude and Inclination |
122 nautical miles/51.6 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Processing
continues on schedule toward next week’s planned
orbiter/external tank mate operation. Leak checks of Endeavour’s
crew module and external airlock are complete. Auxiliary power
unit controller checks are also complete.
Last Friday, Endeavour’s payload
bay doors were cycled and over the weekend the orbiter’s midbody
was cleaned. Today, technicians will close the orbiter’s payload
bay doors in preparation for rollout. Closeouts continue in the
forward and aft compartments. |
|
|
|
MISSION:
STS-109
-- HST
Servicing Mission 3B |
| Vehicle |
Columbia/OV-102 |
| Target KSC Launch
Date/Time |
Feb. 14, 2002 at
1:43 p.m. EST |
| Target KSC Landing
Date/Time |
Feb. 25, 2002 at
11:40 a.m. |
| Mission Duration |
11 days |
| Crew |
Altman, Carey,
Grunsfeld, Currie, Newman, Linnehan, Massimino |
| Orbital Insertion
Altitude and Inclination |
308
nautical miles/28.5 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Over
the weekend, technicians completed alignment work on the heads-up
display (HUD) located on the commander’s side of Columbia’s
cockpit. This coming weekend, workers will complete the same work
on the pilot’s HUD. Auxiliary power unit leak checks are in work
this week, along with orbiter maneuvering system electrical
verifications. |
| |
|
MISSION:
STS-110
-- 13th
ISS Flight (8A) - ITS S0, MT |
| Vehicle |
Atlantis/OV-104 |
| Target KSC Launch Date/Time |
March 21, 2002 |
| Target KSC Landing Date/Time |
April 1, 2002 |
| Mission Duration |
11 days |
| Crew |
Bloomfield, Frick,
Ross, Smith, Ochoa, Morin, Walheim |
| Orbital Insertion Altitude
and Inclination |
122 nautical miles
/51.6 degrees |
|
|
Shuttle
Processing Note (previous notes) |
| Workers
have begun planned powered down modifications on orbiter
Atlantis. This week, work to upgrade the orbiter’s mass
memory units is under way. Technicians are also replacing
window No. 7. Atlantis will resume powered work in
mid-December.
|
|
|
|
STRUCTURAL
INSPECTION & MODIFICATION PERIOD |
|
|
|
|
|
|
Shuttle Processing Note (previous
notes) |
|
Orbiter Discovery remains in temporary storage through late October. Discovery is scheduled to begin a thorough structural inspection and modification period. Shuttle managers continue to assess the content, schedule and location of this planned work period. |
| |
|