MISSION:
STS-108 --
12th ISS
Flight (UF1) - Raffaello MPLM |
| Vehicle |
Endeavour/OV-105 |
| Target KSC Launch
Date/Time |
Nov. 29, 2001 at 7:35
p.m. EST |
| Target KSC Landing
Date/Time |
Dec. 10, 2001 at
2:56 p.m. |
| Mission Duration |
11 days |
| Crew |
Gorie, Kelly,
Godwin, Tani; (ISS-4 up) Onufrienko, Bursch, Walz; (ISS-3
down) Culbertson, Dezhurov, Tyurin |
| Orbital Insertion
Altitude and Inclination |
122 nautical miles/51.6 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Technicians are preparing orbiter Endeavour for its move to the Vehicle Assembly Building. The orbiter's crew module and aft compartment are undergoing closeout work today. Aft leak checks and pressure tests are scheduled for later this week. |
|
|
|
MISSION:
STS-109
-- HST
Servicing Mission 3B |
| Vehicle |
Columbia/OV-102 |
| Target KSC Launch
Date/Time |
Feb. 14, 2002 at
1:43 p.m. EST |
| Target KSC Landing
Date/Time |
Feb. 25, 2002 at
11:40 a.m. |
| Mission Duration |
11 days |
| Crew |
Altman, Carey,
Grunsfeld, Currie, Newman, Linnehan, Massimino |
| Orbital Insertion
Altitude and Inclination |
308
nautical miles/28.5 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Auxiliary power unit exhaust duct leak checks are complete, along with testing of Columbia's Ku band system. Testing of the orbiter's waste containment system are ongoing. Auxiliary power unit strut inspections are in work and orbital maneuvering system electrical verifications continue. Over the weekend, technicians will resume alignment work on the pilot's heads-up display. |
| |
|
MISSION:
STS-110
-- 13th
ISS Flight (8A) - ITS S0, MT |
| Vehicle |
Atlantis/OV-104 |
| Target KSC Launch Date/Time |
March 21, 2002 |
| Target KSC Landing Date/Time |
April 1, 2002 |
| Mission Duration |
11 days |
| Crew |
Bloomfield, Frick,
Ross, Smith, Ochoa, Morin, Walheim |
| Orbital Insertion Altitude
and Inclination |
122 nautical miles
/51.6 degrees |
|
|
Shuttle
Processing Note (previous notes) |
| Power down modifications are in progress on orbiter Atlantis. Workers are upgrading the orbiter's mass memory units and performing a monoball wiring harness enhancement. Atlantis will resume powered work in mid-December.
|
|
|
|
STRUCTURAL
INSPECTION & MODIFICATION PERIOD |
|
|
|
|
|
|
Shuttle Processing Note (previous
notes) |
|
Orbiter Discovery remains in temporary storage through late October. Discovery is scheduled to begin a thorough structural inspection and modification period. Shuttle managers continue to assess the content, schedule and location of this planned work period. |
| |
|