MISSION:
STS-108 --
12th ISS
Flight (UF1) - Raffaello MPLM |
| Vehicle |
Endeavour/OV-105 |
| Target KSC Launch
Date/Time |
Nov. 29, 2001 at 8:05
p.m. EST |
| Target KSC Landing
Date/Time |
Dec. 10, 2001 at 3:26
p.m. EST |
| Mission Duration |
11 days |
| Crew |
Gorie, Kelly,
Godwin, Tani; (ISS-4 up) Onufrienko, Bursch, Walz; (ISS-3
down) Culbertson, Dezhurov, Tyurin |
| Orbital Insertion
Altitude and Inclination |
122 nautical miles/51.6 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Technicians will conclude work on Endeavour's auxiliary power unit (APU) tank struts Friday. Saturday, workers will connect APU lines and begin leak checks. Main engine installation is scheduled to begin Monday. Technicians continue installation of an enhanced monoball wiring harness that will improve processing efficiency. |
|
|
|
MISSION:
STS-109
-- HST
Servicing Mission 3B |
| Vehicle |
Columbia/OV-102 |
| Target KSC Launch
Date/Time |
Jan. 17, 2002 at 3:52
a.m. EST (under review) |
| Target KSC Landing
Date/Time |
Jan. 28, 2002 |
| Mission Duration |
11 days |
| Crew |
Altman, Carey,
Grunsfeld, Currie, Newman, Linnehan, Massimino |
| Orbital Insertion
Altitude and Inclination |
308
nautical miles/28.5 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Columbia's left-hand orbiter maneuvering system (OMS) pod is undergoing routine inspection prior to being installed early next week. Forward reaction control system installation occurs next week as well. Technicians are preparing to install Columbia's auxiliary power units and inertial measurement units. |
| |
|
MISSION:
STS-110
-- 13th
ISS Flight (8A) - ITS S0, MT |
| Vehicle |
Atlantis/OV-104 |
| Target KSC Launch Date/Time |
Feb. 28, 2002 (under
review) |
| Target KSC Landing Date/Time |
March 9, 2002 |
| Mission Duration |
9 days |
| Crew |
Bloomfield, Frick,
Ross, Smith, Ochoa, Morin, Walheim |
| Orbital Insertion Altitude
and Inclination |
122 nautical miles
/51.6 degrees |
|
|
Shuttle
Processing Note (previous notes) |
| Atlantis' payload bay doors are open and technicians have resumed work in the orbiter's midbody. Workers will replace a thruster on Atlantis' reaction control system next week.
|
|
|
|
STRUCTURAL
INSPECTION & MODIFICATION PERIOD |
|
|
|
|
|
|
Shuttle Processing Note (previous
notes) |
Orbiter Discovery remains in temporary storage through late October.
Orbiter Discovery is scheduled to begin a thorough structural inspection and modification period. Shuttle managers continue to assess the content, schedule and location of this planned work period. |
| |
|