|
|
|
MISSION:
STS-110
-- 13th
ISS Flight (8A) - ITS S0 TRUSS, MOBILE TRANSPORTER |
| Vehicle |
Atlantis/OV-104 |
| KSC Launch Date |
April 8, 2002 |
| Launch Time |
4:44:19 p.m. |
| Target KSC Landing Date/Time |
April 19, 2002 at
12:46 p.m. |
| Mission Duration |
11 days |
| Crew |
Bloomfield, Frick,
Ross, Smith, Ochoa, Morin, Walheim |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
|
Shuttle
Processing Note (previous notes) |
Shuttle Atlantis was successfully launched Monday, April 8 at 4:44 p.m. carrying the seven STS-110 crewmembers on their 11-day construction mission to the International Space Station. On-orbit operations began ahead of schedule on the International Space Station today with astronauts Rex Walheim and Steve Smith performing the first of four mission space walks to install the S-0 Truss and Canadarm 2 Mobile Transporter.
Retrieval Ships Liberty Star and Freedom Star returned to Cape Canaveral yesterday with the twin Solid Rocket Boosters in tow. Recovery operations went smoothly and there were no booster anomalies.. |
|
|
|
MISSION:
STS-111 --
14th ISS
Flight (UF2) - MPLM |
| Vehicle |
Endeavour/OV-105 |
| Target KSC Launch
Date/Time |
May 31, 2002 |
| Target KSC Landing
Date/Time |
June 10, 2002 |
| Crew |
Cockrell,
Lockhart, Chang-Diaz, Perrin; (ISS-5 up) Korzun, Whitson,
Treschev; (ISS-4
down) Onufrienko, Bursch, Walz |
| Orbital Insertion
Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Prelaunch operations with Shuttle Endeavour continue in the Orbiter Processing Facility (OPF). Work in progress includes preparations for final payload bay door closure and installation of the External Tank door power drive units. Technicians have replaced six bolts on the Orbiter Maneuvering System engine flange that did not meet specifications. |
|
|
|
MISSION:
STS-107
-- SPACEHAB/Freestar
Research Mission |
| Vehicle |
Columbia/OV-102 |
| Target KSC Launch
Date/Time |
July 19, 2002 |
| Target KSC Landing
Date/Time |
August 3, 2002 |
| Mission Duration |
16 days |
| Crew |
Husband, McCool,
Anderson, Chawla, Brown, Clark, Ramon |
| Orbital Insertion
Altitude/ Inclination |
150
nautical miles/39 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Shuttle Mission managers have rescheduled the launch of the STS-107 Spacehab/Freestar Research Mission to July 19 to allow additional time to complete orbiter processing operations. Preparations are underway with Columbia in the OPF to re-service Freon coolant loop No. 1 after the line was purged to remove some trapped contaminates. X-ray inspections of coolant loop No. 2 are continuing. A control panel has been removed from the crew compartment to replace a faulty relay. |
|
|
|
ORBITER
MAJOR MODIFICATION PERIOD |
|
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Discovery is in the OPF awaiting the start of its Orbiter Major Modification (OMM) period that is scheduled to begin at the Kennedy Space Center late this summer. |
|
|
|
|