This is an orbiter processing report and does not necessarily reflect the chronological order of upcoming Space Shuttle flights.  Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm for the latest schedule of future Shuttle missions.

 

MISSION: STS-110 -- 13th ISS Flight (8A) - ITS S0 TRUSS, MOBILE TRANSPORTER

Vehicle Atlantis/OV-104
KSC Launch Date April 8, 2002
Launch Time 4:44:19 p.m.
Target KSC Landing Date/Time April 19, 2002 at 12:37 p.m.
Mission Duration 11 days
Crew Bloomfield, Frick, Ross, Smith, Ochoa, Morin, Walheim
Orbital Insertion Altitude/Inclination 122 nautical miles/51.6 degrees
 

Shuttle Processing Note  (previous notes)

Shuttle Atlantis was successfully launched Monday, April 8 at 4:44 p.m. carrying the seven STS-110 crewmembers on their 11-day construction mission to the International Space Station. On-orbit operations continue as scheduled. Landing of Atlantis is scheduled for Friday at about 12:37 p.m. at KSC's Shuttle Landing Facility.
 

MISSION: STS-111 -- 14th ISS Flight (UF2) - MPLM

Vehicle Endeavour/OV-105
Target KSC Launch Date/Time May 31, 2002
Target KSC Landing Date/Time June 12,  2002
Mission Duration 12 days
Crew Cockrell, Lockhart, Chang-Diaz, Perrin; (ISS-5 up) Korzun, Whitson, Treschev; (ISS-4 down) Onufrienko, Bursch, Walz 
Orbital Insertion Altitude/Inclination 122 nautical miles/51.6 degrees
 

Shuttle Processing Note  (previous notes)

Prelaunch operations with Shuttle Endeavour continue in the Orbiter Processing Facility (OPF). Work in progress includes aft closeouts and heat shield clearance checks. Final payload bay door closure will commence tomorrow and final power down will be on Wednesday to support upcoming rollover to the Vehicle Assembly Building.
 

MISSION: STS-107 -- SPACEHAB/Freestar Research Mission

Vehicle Columbia/OV-102
Target KSC Launch Date/Time July 19, 2002
Target KSC Landing Date/Time August 4, 2002
Mission Duration 16 days
Crew Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon 
Orbital Insertion Altitude/ Inclination 150 nautical miles/39 degrees
 

Shuttle Processing Note  (previous notes)

Shuttle Mission managers have rescheduled the launch of the STS-107 Spacehab/Freestar Research Mission to July 19 to allow additional time to complete orbiter processing operations. Freon Coolant Loop No. 1 will be re-serviced on Wednesday.
 

ORBITER MAJOR MODIFICATION PERIOD

Vehicle Discovery/OV-103
 

Shuttle Processing Note  (previous notes)

Discovery is in the OPF awaiting the start of its Orbiter Major Modification (OMM) period that is scheduled to begin at the Kennedy Space Center late this summer.
 

The Kennedy Space Center (KSC) Newsroom offers an electronic subscription service for status reports, news releases and other notices issued from KSC. There are two possible ways to subscribe.  You may send a blank e-mail message to ksc-news_release-subscribe@kscnews.ksc.nasa.gov or follow the instructions on the Web site at http://kscnews.ksc.nasa.gov. The system will confirm the request via e-mail.

 
KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines

Page Last Revised

Page & Curator Information

04/16/2002

Curator: Kay Grinter (Kay.Grinter-1@ksc.nasa.gov) -- InDyne, Inc.
Web Development: JBOSC Web Development Team
A Service of the NASA/KSC External Relations and Business Development Directorate
JoAnn H. Morgan, Director