April 25, 2002

 
2002 Year at a Glance

Status Reports

March Status Reports
 
Note

This is an orbiter processing report and does not necessarily reflect the chronological order of upcoming Space Shuttle flights.  Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm for the latest schedule of future Shuttle missions.

 

MISSION: STS-111 -- 14th ISS Flight (UF2) - MPLM

Vehicle Endeavour/OV-105
Target KSC Launch Date/Time May 30, 2002
Target KSC Landing Date/Time June 11,  2002
Mission Duration 11 days
Crew Cockrell, Lockhart, Chang-Diaz, Perrin; (ISS-5 up) Korzun, Whitson, Treschev; (ISS-4 down) Onufrienko, Bursch, Walz 
Orbital Insertion Altitude/Inclination 122 nautical miles/51.6 degrees
 

Shuttle Processing Note  (previous notes)

Shuttle Endeavour has been mated to the External Tank/Solid Rocket Boosters in the Vehicle Assembly Building (VAB) and the Shuttle Interface Test is being conducted to verify overall status of the STS-111 space vehicle. Final preparations will begin on Friday for Endeavour's rollout to the launch pad next week.
 

MISSION: STS-107 -- SPACEHAB/Freestar Research Mission

Vehicle Columbia/OV-102
Target KSC Launch Date/Time July 19, 2002
Target KSC Landing Date/Time August 4, 2002
Mission Duration 16 days
Crew Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon 
Orbital Insertion Altitude/ Inclination 150 nautical miles/39 degrees
 

Shuttle Processing Note  (previous notes)

In the Orbiter Processing Facility (OPF), the Extended Duration Orbiter pallet has been installed aboard Shuttle Columbia. Shuttle managers have made the decision to change out and retest a cold plate in Payload Bay 5 after several dings were discovered on the plate surface. Freon Coolant Loop No. 2 will be drained today to accommodate the cold plate changeout. Columbia will remain powered down until the cold plate is re-installed and the two freon loops are reserviced.
 

MISSION: STS-112 -- 15th ISS Flight (9A) - BA, ITS S1 TRUSS

Vehicle Atlantis/OV-104
Target KSC Launch Date August 22, 2002
Target KSC Landing Date/Time September 1, 2002
Mission Duration 10 days
Crew Ashby, Melroy, Wolf, Sellers, Magnus, Yurchikhin
Orbital Insertion Altitude/Inclination 122 nautical miles/51.6 degrees
 

Shuttle Processing Note  (previous notes)

Deservicing of Shuttle Atlantis is ongoing in the OPF following the orbiter's return from the highly successful STS-110 mission last week. The heat shield has been removed and preparations are in work to remove the Space Shuttle Main Engines early next week.
 

ORBITER MAJOR MODIFICATION PERIOD

Vehicle Discovery/OV-103
 

Shuttle Processing Note  (previous notes)

Discovery rolled back to the OPF yesterday after a brief storage period in the VAB. The orbiter is scheduled to begin its Major Modification period late this summer.
 

The Kennedy Space Center (KSC) Newsroom offers an electronic subscription service for status reports, news releases and other notices issued from KSC. There are two possible ways to subscribe.  You may send a blank e-mail message to ksc-news_release-subscribe@kscnews.ksc.nasa.gov or follow the instructions on the Web site at http://kscnews.ksc.nasa.gov. The system will confirm the request via e-mail.

 
KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines

Page Last Revised

Page & Curator Information

04/25/2002

Curator: Kay Grinter (Kay.Grinter-1@ksc.nasa.gov) -- InDyne, Inc.
Web Development: JBOSC Web Development Team
A Service of the NASA/KSC External Relations and Business Development Directorate
JoAnn H. Morgan, Director