MISSION:
STS-112
-- 15th
ISS Flight (9A) - BA, ITS S1 |
| Vehicle |
Atlantis/OV-104 |
| Target Launch Date |
September 28, 2002
NET |
| Target Landing Date |
October 9, 2002 |
| Mission Duration |
11 days |
| Crew |
Ashby, Melroy, Wolf,
Sellers, Magnus, Yurchikhin |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
| |
|
Shuttle
Processing Note (previous notes) |
| Processing continues for Atlantis' launch to the International Space Station. Demonstration welds continue prior to starting the work on the cracks in the orbiter's Main Propulsion System (MPS) liquid hydrogen flow liners. Welding repairs are scheduled to take place beginning early Friday morning and continue through Saturday. Polishing of the microscopic rough edges of the holes on the downstream flow liners for all three engines is complete. Technicians will continue to polish the upstream holes using the same procedure. Following successful welding repairs, engine installation is scheduled late next week. Fuel cell single cell voltage test is complete.
|
|
|
|
MISSION:
STS-113 --
16th ISS
Flight (11A) - ITS, P1 |
| Vehicle |
Endeavour/OV-105 |
| Target Launch Date |
November 2, 2002
NET |
| Target Landing Date |
November 13, 2002 |
| Mission Duration |
11 days |
| Crew |
Wetherby, Loria, Lopez-Alergria,
Herrington; (ISS up) Bowersox, Budarin, Pettit; (ISS down) Korzun,
Whitson, Treschev |
| Orbital Insertion Altitude/Inclination |
122
nautical miles/51.6 degrees |
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Processing continues for Endeavour's launch to the International Space Station. After repairs are completed on Atlantis' flow liners, welders will begin similar repairs on Endeavour. Fuel cell water line servicing and replacement of window No. 6 is in work. |
|
|
|
MISSION:
STS-107
-- SPACEHAB/FREESTAR
Microgravity Research Mission |
| Vehicle |
Columbia/OV-102 |
| Target Launch Date |
November 29, 2002
NET |
| Target Landing Date |
December 15, 2002 |
| Target KSC Launch
Date/Time |
November 29, 2002
NET |
| Mission Duration |
16 days |
| Crew |
Husband, McCool,
Anderson, Chawla, Brown, Clark, Ramon |
| Orbital Insertion
Altitude/ Inclination |
150
nautical miles/39 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Nominal processing has been completed in preparation for Columbia's research mission now scheduled for no earlier than November 29. Due to the difference in material and number of slots on Columbia's flow liners, more engineering investigation is needed before a final repair option is selected. |
|
|
|
ORBITER
MAJOR MODIFICATION PERIOD |
|
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Discovery is awaiting the start of its Orbiter Major Modification period that is scheduled to begin at the Kennedy Space Center late this summer. |
|
|
|