MISSION:
STS-112
-- 15th
ISS Flight (9A) - BA, ITS S1 |
| Vehicle |
Atlantis/OV-104 |
| Target Launch Date |
October 2, 2002
NET |
| Target Landing Date |
October 13, 2002 |
| Mission Duration |
11 days |
| Crew |
Ashby, Melroy, Wolf,
Sellers, Magnus, Yurchikhin |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
| |
|
Shuttle
Processing Note (previous notes) |
Nominal processing continues for Atlantis’ launch to the International Space Station now scheduled for no earlier than Oct. 2. Closeouts of the orbiter’s aft compartment are in work and Hydraulic/Flight Control Checkout is scheduled for this week.
Engineering evaluation continues on the cracks found in the bearings located in the JEL (jacking, equalization and leveling) cylinders on Crawler Transporter No. 2. Technicians have removed and replaced 14 of the 32 bearings and reinstalled the seven cylinders in Crawler No. 2. Four additional cylinders are in the process of being refurbished. Two more cylinders will be removed today. The remaining bearings will be manufactured and delivered in time to support the scheduled rollout for an Oct. 2 launch.
|
|
|
|
MISSION:
STS-113 --
16th ISS
Flight (11A) - ITS, P1 |
| Vehicle |
Endeavour/OV-105 |
| Target Launch Date |
November 2, 2002 |
| Target Landing Date |
November 13 |
| Mission Duration |
11 days |
| Crew |
Wetherbee, Lockhart,
Lopez-Alegria,
Herrington; (ISS up) Bowersox, Budarin, Pettit; (ISS down) Korzun,
Whitson, Treschev |
| Orbital Insertion Altitude/Inclination |
122
nautical miles/51.6 degrees |
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Processing continues for Endeavour’s launch to the International Space Station. Main Propulsion System flow liner crack welding has been successfully completed. Preparations for Space Shuttle Main Engine installation are in work with engine installation beginning as early as this evening. |
|
|
|
MISSION:
STS-107
-- SPACEHAB/FREESTAR
Microgravity Research Mission |
| Vehicle |
Columbia/OV-102 |
| Target Launch Date |
January 16, 2003
NET |
| Target Landing Date |
TBD |
| Mission Duration |
16 days |
| Crew |
Husband, McCool,
Anderson, Chawla, Brown, Clark, Ramon |
| Orbital Insertion
Altitude/ Inclination |
150
nautical miles/39 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Nominal processing has been completed in preparation for Columbia’s research mission now scheduled for no earlier than Jan. 16. |
|
|
|
ORBITER
MAJOR MODIFICATION PERIOD |
|
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Sept. 1 has been identified as the date to begin Discovery's Orbiter Major Modification period at KSC. |
|
|
|