MISSION:
STS-112
-- 15th
ISS Flight (9A) - BA, ITS S1 |
| Vehicle |
Atlantis/OV-104 |
| Target Launch Date |
October 2, 2002
NET |
| Target Landing Date |
October 13, 2002 |
| Mission Duration |
11 days |
| Crew |
Ashby, Melroy, Wolf,
Sellers, Magnus, Yurchikhin |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
| |
|
Shuttle
Processing Note (previous notes) |
Nominal processing continues for Atlantis’ launch to the International Space Station now scheduled for no earlier than Oct. 2. Closeouts of the orbiter’s aft compartment have been completed in preparation for the orbiter to roll over and be mated to its external tank and solid rocket boosters.
Technicians have removed and replaced 24 of the 32 bearings located in the JEL (jacking, equalization and leveling) cylinders and reinstalled the 12 cylinders on Crawler Transporter No. 2. The four remaining cylinders have been removed for refurbishment. Two cylinders will be reinstalled today, with the final two scheduled for installation tomorrow. The initial shipment of remanufactured bearings
will arrive today from the vendor.
|
|
|
|
MISSION:
STS-113 --
16th ISS
Flight (11A) - ITS, P1 |
| Vehicle |
Endeavour/OV-105 |
| Target Launch Date |
November 2, 2002 |
| Target Landing Date |
November 13 |
| Mission Duration |
11 days |
| Crew |
Wetherbee, Lockhart,
Lopez-Alegria,
Herrington; (ISS up) Bowersox, Budarin, Pettit; (ISS down) Korzun,
Whitson, Treschev |
| Orbital Insertion Altitude/Inclination |
122
nautical miles/51.6 degrees |
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Endeavour continues to be processed for its upcoming launch to the International Space Station. Space Shuttle Main Engine (SSME) installation is complete. Main Propulsion System and SSME leak checks, and ammonia servicing are scheduled for this week. |
|
|
|
MISSION:
STS-107
-- SPACEHAB/FREESTAR
Microgravity Research Mission |
| Vehicle |
Columbia/OV-102 |
| Target Launch Date |
January 16, 2003
NET |
| Target Landing Date |
February 1, 2003 |
| Mission Duration |
16 days |
| Crew |
Husband, McCool,
Anderson, Chawla, Brown, Clark, Ramon |
| Orbital Insertion
Altitude/ Inclination |
150
nautical miles/39 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Nominal processing has been completed in preparation for Columbia’s research mission now scheduled for no earlier than Jan. 16. |
|
|
|
ORBITER
MAJOR MODIFICATION PERIOD |
|
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Sept. 1 has been identified as the date to begin Discovery's Orbiter Major Modification period at KSC. |
|
|
|