MISSION:
STS-109
-- HST
Servicing Mission 3B |
| Vehicle |
Columbia/OV-102 |
| Target KSC Launch
Date/Time |
Feb. 28, 2002 |
| Target KSC Landing
Date/Time |
March 11, 2002 |
| Mission Duration |
11 days |
| Crew |
Altman, Carey,
Grunsfeld, Currie, Newman, Linnehan, Massimino |
| Orbital Insertion
Altitude/ Inclination |
308
nautical miles/28.5 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| The rollout of Shuttle Columbia from the Vehicle Assembly Building (VAB) high bay to Pad A has been rescheduled for Monday, Jan. 28, with first motion at 7 a.m.. Verification testing of the operation of the steering linkage in all four of the crawler-transporter truck drives is in progress. No impact is expected on the STS-109 launch date or the milestone processing events leading up to it. |
| |
|
MISSION:
STS-110
-- 13th
ISS Flight (8A) - ITS S0 TRUSS, MOBILE TRANSPORTER |
| Vehicle |
Atlantis/OV-104 |
| Target KSC Launch Date/Time |
April 4, 2002 |
| Target KSC Landing Date/Time |
April 15, 2002 |
| Mission Duration |
11 days |
| Crew |
Bloomfield, Frick,
Ross, Smith, Ochoa, Morin, Walheim |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
|
Shuttle
Processing Note (previous notes) |
| Shuttle Atlantis is undergoing prelaunch preparations in the Orbiter Processing Facility (OPF). The payload premate test is complete and main propulsion leak checks are in work. Inspection of the condition of attach point No.5 continues after the left-hand Orbiter Maneuvering System (OMS) pod was removed last Wednesday. |
|
|
|
MISSION:
STS-111 --
14th ISS
Flight (UF2) - MPLM |
| Vehicle |
Endeavour/OV-105 |
| Target KSC Launch
Date/Time |
May 2, 2002 |
| Target KSC Landing
Date/Time |
May 13, 2002 |
| Crew |
Cockrell,
Lockhart, Chang-Diaz, Perrin; (ISS-5 up) Korzun, Whitson,
Treschev; (ISS-4
down) Onufrienko, Bursch, Walz |
| Orbital Insertion
Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Auxiliary Propulsion System (APS) leak and functional checks are being conducted on Shuttle Endeavour in the OPF. The pitch actuator for Main Engine No. 1 is being removed to repair a faulty connector. |
|
|
|
STRUCTURAL
INSPECTION & MODIFICATION PERIOD |
|
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Discovery is scheduled to be moved back to the OPF from temporary storage in the VAB high bay on Monday. No decision has been made by Shuttle managers on the content, schedule and location for the structural inspection and modification down period. |
|
|
|
|