|
MISSION:
STS-107
-- SPACEHAB/FREESTAR
Microgravity Research Mission |
| Vehicle |
Columbia/OV-102 |
| Target KSC Launch
Date/Time |
TBD |
| Mission Duration |
16 days |
| Crew |
Husband, McCool,
Anderson, Chawla, Brown, Clark, Ramon |
| Orbital Insertion
Altitude/ Inclination |
150
nautical miles/39 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Following inspections of Columbia's Main Propulsion System (MPS) flow liners that identified three cracks on engine No. 2 liquid hydrogen flow liner, mission managers delayed the launch date until a full engineering analysis is complete. |
|
|
|
MISSION:
STS-112
-- 15th
ISS Flight (9A) - BA, ITS S1 |
| Vehicle |
Atlantis/OV-104 |
| Target KSC Launch Date |
August 22, 2002
(under review) |
| Mission Duration |
10 days |
| Crew |
Ashby, Melroy, Wolf,
Sellers, Magnus, Yurchikhin |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
| |
|
Shuttle
Processing Note (previous notes) |
| Processing continues for Atlantis' launch to the International Space Station. Controller tests are complete on Auxiliary Power Units No. 2 and 3. Left-hand Orbital Maneuvering System (OMS) engine heat shield installation is scheduled for today. Inspections of Atlantis identified three cracks on engine No. 1 liquid hydrogen flow liner.
|
|
|
|
MISSION:
STS-113 --
16th ISS
Flight (11A) - ITS, P1 |
| Vehicle |
Endeavour/OV-105 |
| KSC Launch Date/Time |
October 6, 2002 (under
review) |
| Crew |
Wetherby, Loria, Lopez-Alergria,
Herrington; (ISS up) Bowersox, Budarin, Thomas; (ISS down) Korzun,
Whitson, Treschev |
| Orbital Insertion Altitude/Inclination |
122
nautical miles/51.6 degrees |
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Eddy current testing of Endeavour's liquid oxygen and hydrogen flow liners are complete. Ultrasound and borescope inspections continue. Technicians have identified two cracks, the first on engine one and the second on engine two liquid hydrogen flow liner. The cracks are similar to the ones discovered on the other three orbiters. In parallel to the flow liner inspections, Shuttle Endeavour processing continues for its next mission to the International Space Station. Removal of the Multi-Purpose Logistics Module from the payload bay is scheduled for today. |
|
|
|
ORBITER
MAJOR MODIFICATION PERIOD |
|
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Discovery is awaiting the start of its Orbiter Major Modification (OMM) period that is scheduled to begin at the Kennedy Space Center late this summer. Inspections of Discovery identified three cracks on engine No. 1 liquid hydrogen flow liner. |
|
|
|