MISSION:
STS-107
-- SPACEHAB/FREESTAR
Microgravity Research Mission |
| Vehicle |
Columbia/OV-102 |
| Target KSC Launch
Date/Time |
TBD |
| Mission Duration |
16 days |
| Crew |
Husband, McCool,
Anderson, Chawla, Brown, Clark, Ramon |
| Orbital Insertion
Altitude/ Inclination |
150
nautical miles/39 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Following inspections of Columbia's Main Propulsion System (MPS) flow liners that identified three cracks on engine No. 2 liquid hydrogen flow liner, mission managers delayed the launch date until a full engineering analysis could be completed. Nominal processing has been finished in preparation for Columbia's research mission and after a decision has been made as to how to resolve the flow liner issues, a launch date will be set. |
|
|
|
MISSION:
STS-112
-- 15th
ISS Flight (9A) - BA, ITS S1 |
| Vehicle |
Atlantis/OV-104 |
| Target KSC Launch Date |
TBD |
| Mission Duration |
10 days |
| Crew |
Ashby, Melroy, Wolf,
Sellers, Magnus, Yurchikhin |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
| |
|
Shuttle
Processing Note (previous notes) |
| Processing continues for Atlantis' launch to the International Space Station. Orbital Maneuvering System (OMS)/Reaction Control System (RCS) electrical verification is in work and OMS/RCS flight controls checkout is complete. Multifunction Electronic Display Subsystem (MEDS) checkout is scheduled for this week. Atlantis' payload bay doors were closed last week in preparation for rollover once the flow liner issue is resolved.
|
|
|
|
MISSION:
STS-113 --
16th ISS
Flight (11A) - ITS, P1 |
| Vehicle |
Endeavour/OV-105 |
| KSC Launch Date/Time |
TBD |
| Crew |
Wetherby, Loria, Lopez-Alergria,
Herrington; (ISS up) Bowersox, Budarin, Thomas; (ISS down) Korzun,
Whitson, Treschev |
| Orbital Insertion Altitude/Inclination |
122
nautical miles/51.6 degrees |
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Processing continues for Endeavour's launch to the International Space Station and will be scheduled once the flow liner issue is resolved. The Multi-Purpose Logistics Module was removed from the payload bay, as deservicing continues from Endeavour's previous mission. Fuel cell verification is complete. OMS pod checkout and replacement of windows No. 6 and 8 are in work. |
|
|
|
ORBITER
MAJOR MODIFICATION PERIOD |
|
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Discovery is awaiting the start of its Orbiter Major Modification (OMM) period that is scheduled to begin at the Kennedy Space Center late this summer. |
|
|
|