MISSION: STS-111 -- 14th ISS Flight (UF2) - MPLM

Vehicle Endeavour/OV-105
Target KSC Launch Date/Time June 5, 2002 at 5:22:49 p.m. EDT
Target KSC Landing Date/Time June 17,  2002 at 1:00 p.m. EDT
Mission Duration 12 days
Crew Cockrell, Lockhart, Chang-Diaz, Perrin; (ISS-5 up) Korzun, Whitson, Treschev; (ISS-4 down) Onufrienko, Bursch, Walz 
Orbital Insertion Altitude/Inclination 122 nautical miles/51.6 degrees
 

Shuttle Processing Note  (previous notes)

Everything continues to perform well aboard Endeavour during docked operations at the International Space Station. The third spacewalk of the STS-111 mission is scheduled for today, where Astronauts Philippe Perrin and Franklin Chang-Díaz will replace the Space Shuttle Remote Manipulator System wrist roll joint. Undocking is scheduled for Saturday with the first planned landing opportunity on Monday, June 17 at 1:00 p.m. The landing time has changed due to cross-range limitations on an earlier landing opportunity.
 

MISSION: STS-107 -- SPACEHAB/Freestar Research Mission

Vehicle Columbia/OV-102
Target KSC Launch Date/Time July 19, 2002
Target KSC Landing Date/Time August 4, 2002
Mission Duration 16 days
Crew Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon 
Orbital Insertion Altitude/ Inclination 150 nautical miles/39 degrees
 

Shuttle Processing Note  (previous notes)

At a meeting this morning, mission managers determined that processing for the STS-107 microgravity research mission would continue to proceed toward a July 19 launch date. Landing gear, nose wheel steering and brake functional tests, as well as the four-inch liquid hydrogen disconnect connections are complete. Integrated hydraulic checkout is in work. The doors on the payload bay, containing the SPACEHAB / FREESTAR payload, are scheduled to be closed for flight tomorrow and will not be reopened at the pad prior to launch.
 

MISSION: STS-112 -- 15th ISS Flight (9A) - BA, ITS S1 

Vehicle Atlantis/OV-104
Target KSC Launch Date August 22, 2002
Target KSC Landing Date/Time September 1, 2002
Mission Duration 10 days
Crew Ashby, Melroy, Wolf, Sellers, Magnus, Yurchikhin
Orbital Insertion Altitude/Inclination 122 nautical miles/51.6 degrees
 

Shuttle Processing Note  (previous notes)

Processing continues for Atlantis' scheduled launch to the International Space Station this August. Ammonia servicing and the payload premate test are complete. Replacement of fuel cell No. 2 is in work.
 

ORBITER MAJOR MODIFICATION PERIOD

Vehicle Discovery/OV-103
 

Shuttle Processing Note  (previous notes)

Discovery is in the OPF awaiting the start of its Orbiter Major Modification (OMM) period that is scheduled to begin at the Kennedy Space Center late this summer.
 

The Kennedy Space Center (KSC) Newsroom offers an electronic subscription service for status reports, news releases and other notices issued from KSC. There are two possible ways to subscribe.  You may send a blank e-mail message to ksc-news_release-subscribe@kscnews.ksc.nasa.gov or follow the instructions on the Web site at http://kscnews.ksc.nasa.gov. The system will confirm the request via e-mail.

 
KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines

Page Last Revised

Page & Curator Information

06/13/2002

Curator: Kay Grinter (Kay.Grinter-1@ksc.nasa.gov) -- InDyne, Inc.
Web Development: JBOSC Web Development Team
A Service of the NASA/KSC External Relations and Business Development Directorate
JoAnn H. Morgan, Director