|
MISSION:
STS-107
-- SPACEHAB/Freestar
Microgravity Research Mission |
| Vehicle |
Columbia/OV-102 |
| Target KSC Launch
Date/Time |
July 19, 2002 |
| Launch Period |
9 a.m. - 1 p.m.
EDT |
| Target KSC Landing
Date/Time |
August 4, 2002 |
| Mission Duration |
16 days |
| Crew |
Husband, McCool,
Anderson, Chawla, Brown, Clark, Ramon |
| Orbital Insertion
Altitude/ Inclination |
150
nautical miles/39 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Processing continues on schedule for the STS-107 microgravity research mission. Aft closeouts are complete and forward closeouts are in work. Final Orbiter power down is scheduled for late this evening in preparation for rollover to the Vehicle Assembly Building. |
|
|
|
MISSION:
STS-112
-- 15th
ISS Flight (9A) - BA, ITS S1 |
| Vehicle |
Atlantis/OV-104 |
| Target KSC Launch Date |
August 22, 2002 |
| Target KSC Landing Date/Time |
September 1, 2002 |
| Mission Duration |
10 days |
| Crew |
Ashby, Melroy, Wolf,
Sellers, Magnus, Yurchikhin |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
| |
|
Shuttle
Processing Note (previous notes) |
| Processing continues for Atlantis' scheduled launch to the International Space Station this August. During visual inspections, technicians noticed a small crack in the Main Propulsion System (MPS) LH2 flow liner leading to engine No. 1. After noticing the crack, tests were performed and two more cracks were identified on the same flow liner. Workers are performing further testing to determine the cause and if corrective action is required.
|
|
|
|
ORBITER
MAJOR MODIFICATION PERIOD |
|
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Discovery was moved from the VAB back to the OPF this morning, where it will remain until the arrival of Endeavour at KSC. As part of an analysis of the flow liner cracks found on Atlantis, similar inspections will be performed on Discovery this weekend. |
|
|
|