|
|
|
MISSION:
STS-110
-- 13th
ISS Flight (8A) - ITS S0 TRUSS, MOBILE TRANSPORTER |
| Vehicle |
Atlantis/OV-104 |
| Target KSC Launch Date/Time |
April 4, 2002 |
| Target KSC Landing Date/Time |
April 15, 2002 |
| Mission Duration |
11 days |
| Crew |
Bloomfield, Frick,
Ross, Smith, Ochoa, Morin, Walheim |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
|
Shuttle
Processing Note (previous notes) |
| Shuttle
Atlantis remains on schedule for the launch of the STS-110 mission
to the International Space Station on April 4. At the launch pad,
the Terminal Countdown Demonstration Test and the helium signature
test are underway. Hypergolic fuel loading is scheduled for
later this week and the Rotating Service Structure will be moved to
the parked position on Friday for the Auxiliary Power Unit (APU) hot
fire. X-rays of the APU hydraulic pump bolts in the orbiter and
boosters are complete and are under evaluation. |
|
|
|
MISSION:
STS-111 --
14th ISS
Flight (UF2) - MPLM |
| Vehicle |
Endeavour/OV-105 |
| Target KSC Launch
Date/Time |
May 6, 2002 |
| Target KSC Landing
Date/Time |
May 17, 2002 |
| Crew |
Cockrell,
Lockhart, Chang-Diaz, Perrin; (ISS-5 up) Korzun, Whitson,
Treschev; (ISS-4
down) Onufrienko, Bursch, Walz |
| Orbital Insertion
Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Shuttle
Endeavour is in the Orbiter Processing Facility (OPF) undergoing
final checkouts for the STS-111 launch in May. The Integrated
Hydraulic/Flight Control test and payload bay closeouts are in work. |
|
|
|
MISSION:
STS-107
-- Freestar
Research Mission |
| Vehicle |
Columbia/OV-102 |
| Target KSC Launch
Date/Time |
July 11, 2002 |
| Target KSC Landing
Date/Time |
July 27, 2002 |
| Mission Duration |
16 days |
| Crew |
Husband, McCool,
Anderson, Chawla, Brown, Clark, Ramon |
| Orbital Insertion
Altitude/ Inclination |
150
nautical miles/39 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| In
the OPF, the payload doors of Shuttle Columbia have been
opened and work is underway to remove the Hubble payload
components onboard. X-ray and ultra-sound testing of freon
coolant loops No. 1 and No. 2 are continuing to identify and
isolate the contamination that caused degraded performance of
freon loop No.1 during the recently completed STS-109 mission. |
|
|
|
ORBITER
MAJOR MODIFICATION PERIOD |
|
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Discovery is in the OPF awaiting the start of its Orbiter Major Modification (OMM) period that is scheduled to begin at the Kennedy Space Center late this summer.
|
|
|
|
|