|
|
|
MISSION:
STS-110
-- 13th
ISS Flight (8A) - ITS S0 TRUSS, MOBILE TRANSPORTER |
| Vehicle |
Atlantis/OV-104 |
| Target KSC Launch Date/Time |
April 4, 2002;
Launch period: 2 p.m. to 6 p.m. EST |
| Target KSC Landing Date/Time |
April 15, 2002 |
| Mission Duration |
11 days |
| Crew |
Bloomfield, Frick,
Ross, Smith, Ochoa, Morin, Walheim |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
|
Shuttle
Processing Note (previous notes) |
| Shuttle
Atlantis remains on schedule for the launch of the STS-110 mission
to the International Space Station on April 4. Over the weekend,
work was completed on the newly installed Master Events Controller
No. 1 and the right hand Solid Rocket Booster Auxiliary Power System
hydraulic pump. The STS-110 payload was delivered to the pad on
Saturday and will be installed onboard Atlantis later this week.
Other work scheduled for the week includes installing the EVA space
suits, updating the mass memory unit and ordnance installation.. |
|
|
|
MISSION:
STS-111 --
14th ISS
Flight (UF2) - MPLM |
| Vehicle |
Endeavour/OV-105 |
| Target KSC Launch
Date/Time |
No earlier than
May 31, 2002 |
| Target KSC Landing
Date/Time |
June 10, 2002 |
| Crew |
Cockrell,
Lockhart, Chang-Diaz, Perrin; (ISS-5 up) Korzun, Whitson,
Treschev; (ISS-4
down) Onufrienko, Bursch, Walz |
| Orbital Insertion
Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| As
a result of the program decision to postpone the STS-111 mission to
no earlier than May 31 to allow time for a wrist roll joint
replacement to be installed in the cargo bay for the Space Station’s
Canadarm2, Shuttle Endeavour will remain in the Orbiter Processing
Facility (OPF) undergoing final launch readiness preparations. Work
in progress includes integrity checks of the potable water system
that was serviced late last week. |
|
|
|
MISSION:
STS-107
-- SPACEHAB/Freestar
Research Mission |
| Vehicle |
Columbia/OV-102 |
| Target KSC Launch
Date/Time |
NET July 11, 2002 |
| Target KSC Landing
Date/Time |
July 27, 2002 |
| Mission Duration |
16 days |
| Crew |
Husband, McCool,
Anderson, Chawla, Brown, Clark, Ramon |
| Orbital Insertion
Altitude/ Inclination |
150
nautical miles/39 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| De-servicing
of Shuttle Columbia continues in the OPF in preparation for
the processing flow for the STS-107 Spacehab/Freestar mission
in July. The offload of hypergolic residual propellants is
complete and main engine removal is scheduled for later this
week. X-ray inspections of the freon coolant loops are in
progress. |
|
|
|
ORBITER
MAJOR MODIFICATION PERIOD |
|
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Discovery is in the OPF awaiting the start of its Orbiter Major Modification (OMM) period that is scheduled to begin at the Kennedy Space Center late this summer.
|
|
|
|
|