This is an orbiter processing report and does not necessarily reflect the chronological order of upcoming Space Shuttle flights. Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm for the latest schedule of future Shuttle missions. |
| |||||||||||||||
|
Shuttle Processing Note (previous notes) |
|||||||||||||||
| Final processing operations continue on schedule with Shuttle Atlantis in preparation for the STS-110 launch to the International Space Station on April 4. Shuttle managers gave a go for the launch following yesterday's comprehensive Flight Readiness Review. At Pad B, the S-Zero Integrated Truss Structure and Mobile Transporter will be installed in the orbiter payload bay today. Other work in progress includes integrity checks of the three EVA suits on board, aft closeouts and External Tank purge operations. The hot fire test of the replacement hydraulic power unit in the right aft Solid Rocket Booster was successfully completed yesterday. | |||||||||||||||
|
The Kennedy Space Center (KSC) Newsroom offers an electronic subscription service for status reports, news releases and other notices issued from KSC. There are two possible ways to subscribe. You may send a blank e-mail message to ksc-news_release-subscribe@kscnews.ksc.nasa.gov or follow the instructions on the Web site at http://kscnews.ksc.nasa.gov. The system will confirm the request via e-mail. |
| KSC Home Page | Site Search | FAQ's | Site Survey | Customer Forum | NASA Centers | Privacy Statement | Headlines |
|
Page Last Revised |
Page & Curator Information |
|---|---|
|
03/27/2002 |
Curator: Kay Grinter (Kay.Grinter-1@ksc.nasa.gov)
-- InDyne, Inc. |