MISSION:
STS-107
-- SPACEHAB/Freestar
Research Mission |
| Vehicle |
Columbia/OV-102 |
| Target KSC Launch
Date/Time |
July 19, 2002 |
| Target KSC Landing
Date/Time |
August 4, 2002 |
| Mission Duration |
16 days |
| Crew |
Husband, McCool,
Anderson, Chawla, Brown, Clark, Ramon |
| Orbital Insertion
Altitude/ Inclination |
150
nautical miles/39 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Processing
for Columbia’s STS-107 microgravity research mission continues in
the Orbiter Processing Facility (OPF). Right-hand Orbital
Maneuvering System pod thruster replacements are complete. Payload
premate test, Auxiliary Power Unit leak and functional test, and
servicing of Freon Loop No. 1 are in work. |
|
|
|
MISSION:
STS-112
-- 15th
ISS Flight (9A) - BA, ITS S1 |
| Vehicle |
Atlantis/OV-104 |
| Target KSC Launch Date |
August 22, 2002 |
| Target KSC Landing Date/Time |
September 1, 2002 |
| Mission Duration |
10 days |
| Crew |
Ashby, Melroy, Wolf,
Sellers, Magnus, Yurchikhin |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
| |
|
Shuttle
Processing Note (previous notes) |
| In
the OPF, processing continues for the schedule launch of Atlantis to the
International Space Station this August. Master Events Controller/Pyro
Initiator test is complete. Orbital Maneuvering System checkout is in
work.
|
|
|
|
ORBITER
MAJOR MODIFICATION PERIOD |
|
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Discovery is in the OPF awaiting the start of its Orbiter Major Modification (OMM) period that is scheduled to begin at the Kennedy Space Center late this summer. |
|
|
|