MISSION:
STS-107
-- SPACEHAB/Freestar
Research Mission |
| Vehicle |
Columbia/OV-102 |
| Target KSC Launch
Date/Time |
July 19, 2002 |
| Target KSC Landing
Date/Time |
August 4, 2002 |
| Mission Duration |
16 days |
| Crew |
Husband, McCool,
Anderson, Chawla, Brown, Clark, Ramon |
| Orbital Insertion
Altitude/ Inclination |
150
nautical miles/39 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Preparations continue in the Orbiter Processing Facility (OPF) for Columbia's STS-107 microgravity research mission. Installation of the SPACEHAB/FREESTAR payload is scheduled for Wednesday of this week. Auxiliary Power Unit leak and functional test and servicing of Freon Loop No. 1 are in work. |
|
|
|
MISSION:
STS-112
-- 15th
ISS Flight (9A) - BA, ITS S1 |
| Vehicle |
Atlantis/OV-104 |
| Target KSC Launch Date |
August 22, 2002 |
| Target KSC Landing Date/Time |
September 1, 2002 |
| Mission Duration |
10 days |
| Crew |
Ashby, Melroy, Wolf,
Sellers, Magnus, Yurchikhin |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
| |
|
Shuttle
Processing Note (previous notes) |
| Atlantis continues to be processed for its scheduled launch to the International Space Station this August. Draining of the Orbiter Maneuvering System (OMS) crossfeed is complete and OMS disconnect and replacement of window No. 2 is in work.
|
|
|
|
ORBITER
MAJOR MODIFICATION PERIOD |
|
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Discovery is in the OPF awaiting the start of its Orbiter Major Modification (OMM) period that is scheduled to begin at the Kennedy Space Center late this summer. |
|
|
|