MISSION:
STS-112
-- 15th
ISS Flight (9A) - S1 Truss Segment |
| Vehicle |
Atlantis/OV-104 |
| Official Launch Date |
October 2, 2002 |
| Official Launch
Time |
3:45:51 p.m. EDT |
| Target Landing Date |
October 18, 2002 at
11:46 a.m. EDT |
| Mission Duration |
11 days |
| Crew |
Ashby, Melroy, Wolf,
Sellers, Magnus, Yurchikhin |
| Orbital Insertion Altitude/Inclination |
122 nautical miles/51.6 degrees |
|
| |
|
Shuttle
Processing Note (previous notes) |
|
The
crew of Space Shuttle Atlantis met up with the crew of the International
Space Station when the orbiter and ISS docked yesterday in preparation of
installation of the S1 Truss Segment.
The
retrieval ships Liberty Star and Freedom Star have returned to Cape
Canaveral with the spent solid rocket booster for engineering inspections.
|
|
|
|
MISSION:
STS-113 --
16th ISS
Flight (11A) - P1 Truss Segment |
| Vehicle |
Endeavour/OV-105 |
| Target Launch Date |
November 10, 2002
NET |
| Target Launch Time |
10:30 p.m. (Nov. 9)
to 2:30 a.m. (Nov. 10) |
| Target Landing Date |
November 20, 2002 |
| Mission Duration |
11 days |
| Crew |
Wetherbee, Lockhart,
Lopez-Alegria,
Herrington; (ISS up) Bowersox, Budarin, Pettit; (ISS down) Korzun,
Whitson, Treschev |
| Orbital Insertion Altitude/Inclination |
122
nautical miles/51.6 degrees |
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| Space
Shuttle
Endeavour
is on the Mobile Launch Platform, mated to the External Tank and
Solid Rocket Boosters.
Preparations
are in work to transport Endeavour to the launch pad to begin the
final phase of processing in anticipation of launch next
month. Mission
managers are keeping an eye on weather conditions as a result of Tropical
Depression Kyle that is heading towards the east coast of Florida.
The P-1 Truss Segment payload was delivered to the pad this
morning.
|
|
|
|
MISSION:
STS-107
-- SPACEHAB/FREESTAR
Microgravity Research Mission |
| Vehicle |
Columbia/OV-102 |
| Target Launch Date |
January 16, 2003
NET |
| Target Landing Date |
February 1, 2003 |
| Mission Duration |
16 days |
| Crew |
Husband, McCool,
Anderson, Chawla, Brown, Clark, Ramon |
| Orbital Insertion
Altitude/ Inclination |
150
nautical miles/39 degrees |
|
| |
|
Shuttle
Processing Note (previous
notes) |
| Columbia
continues processing in preparation for its research mission
scheduled for no earlier than Jan. 16.
Polishing and welding is in work on the flow-liners.
Engine installation is scheduled to begin next Wednesday.
|
|
|
|
ORBITER
MAJOR MODIFICATION PERIOD |
|
|
|
|
|
Shuttle
Processing Note (previous
notes) |
| The Orbiter Major Modification (OMM) period for Discovery continues with wire inspections in the crew module this week. |
|
|
|