John F. Kennedy Space Center Banner NASA Home Page


October 15, 2002

 
2002 Year at a Glance

Status Reports

August Status Reports
 
Note

For the latest Shuttle status on the web visit http://www-pao.ksc.nasa.gov/kscpao/status/stsstat/current.htm.
For the latest launch weather forecast visit http://www-pao.ksc.nasa.gov/kscpao/status/weatstat/forecast.htm.
Visit http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm for the latest schedule of future Shuttle missions.

 

MISSION: STS-112 -- 15th ISS Flight (9A) - S1 Truss Segment 

Vehicle Atlantis/OV-104
Official Launch Date and Time October 2, 2002 at 3:45:51 p.m. EDT
Target Landing Date and Time October 18, 2002 at 11:46 a.m. EDT
Mission Duration 11 days
Crew Ashby, Melroy, Wolf, Sellers, Magnus, Yurchikhin
Orbital Insertion Altitude/Inclination 122 nautical miles/51.6 degrees
 

Shuttle Processing Note  (previous notes)

Atlantis launches on mission STS-112.

T
he crew of Space Shuttle Atlantis will undock with the International Space Station tomorrow and make preparations to return to Earth on Friday after successfully installing the S1 Truss Segment.
 

MISSION: STS-113 -- 16th ISS Flight (11A) - P1 Truss Segment

Vehicle Endeavour/OV-105
Target Launch Date November 10, 2002
Target Launch Period 10:30 p.m. to 2:30 a.m.
Target Landing Date November 20, 2002
Mission Duration 11 days
Crew Wetherbee, Lockhart, Lopez-Alegria, Herrington; (ISS up) Bowersox, Budarin, Pettit; (ISS down) Korzun, Whitson, Treschev 
Orbital Insertion Altitude/Inclination 122 nautical miles/51.6 degrees
 

Shuttle Processing Note  (previous notes)

The P1 Truss Segment is lowered into the payload canister.
Space Shuttle Endeavour rolled out to the launch pad over the weekend and the P-1 truss payload is currently being installed in its payload bay today. Pad Validation is complete. The Terminal Countdown Demonstration Test is currently scheduled for later this week. Preparation for propellant load, scheduled for next week, is currently in work.
 

MISSION: STS-107 -- SPACEHAB/FREESTAR Microgravity Research Mission

Vehicle Columbia/OV-102
Target Launch Date January 16, 2003 NET
Target Landing Date February 1, 2003
Mission Duration 16 days
Crew Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon 
Orbital Insertion Altitude/ Inclination 150 nautical miles/39 degrees
 

Shuttle Processing Note  (previous notes)

Columbia continues processing in preparation for its research mission scheduled for no earlier than Jan. 16. Polishing and welding is in work on the flow liners. Engine installation is scheduled to begin late Friday.
 

ORBITER MAJOR MODIFICATION PERIOD

Vehicle Discovery/OV-103
 

Shuttle Processing Note  (previous notes)

The Orbiter Major Modification (OMM) period for Discovery continues with wire inspections in the crew module this week.
 

The Kennedy Space Center (KSC) Newsroom offers an electronic subscription service for status reports, news releases and other notices issued from KSC. There are two possible ways to subscribe.  You may send a blank e-mail message to ksc-news_release-subscribe@kscnews.ksc.nasa.gov or follow the instructions on the Web site at http://kscnews.ksc.nasa.gov. The system will confirm the request via e-mail.

 
KSC Home Page Site Search FAQ's Site Survey Customer Forum NASA Centers Privacy Statement Headlines

Page Last Revised

Page & Curator Information

10/16/2002

Curator: Kay Grinter (Kay.Grinter-1@ksc.nasa.gov) -- InDyne, Inc.
Web Development: JBOSC Web Development Team
A Service of the NASA/KSC External Relations and Business Development Directorate
JoAnn H. Morgan, Director